Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
If C worked on job Y with times his given efficiency and was assisted by B every day, then find the time taken by C to complete the job Y ?
13 days
days
days
12 days
The correct Answer is:D
With new efficiency C will complete job in = 12 days
3 days work of C and 1 days work of B=1/3
Days required =9 days
Topper's Solved these Questions
Similar Questions
Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
If the ratio of number of days for which B and D worked on job X is 4:3 , then find teh difference between of days for which B and D worked ?View Solution
Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
If A,C abd E worked on job Z for 2 days each and the remaining job was done by B and D. if the ratio of no. days for which B and D worked is in ratio 20:21, then find the number of days for which B worked ?View Solution
Knowledge Check
- Question 1 - Select One
10 persons can do a job in X days. If 20 persons with twice the efficiency can do the same job in 5 days, then find the value of X?
A 40 B 15 C 20 D 30ABBCCADD - Question 2 - Select One
24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
A30B40C25D50 - Question 3 - Select One
A can do a job in 15 days, B in 10 days and C in 30 days. If A is helped by B and C on every third day, then the job will be completed in
A613 daysB813 daysC8 daysD9 days
Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
A and C worked on job Y working alternatively for 10 days. B and D then worked together for 'x' day . if 136 of the job was still remained, then find the value of 'x' ?View Solution
Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
E worked on job 'Z' for 5 dyas and the remaining job was completed by A, B and D who worked on alternate days starting with A followed by B and D in thet order. Find the no. of days B worked for ?View SolutionA,B,C,D and E are five persons to complete jobs X and Y. Line graph shows the data regarding the number of days taken by these persons to complete the job X and Y.
If B worked on job Y with 4/9 times his work efficiency and assisted by D every 3rd day then find the number of days for which B and D worked to complete the job.View SolutionA man take 80 days to complete a job. To complete this job, 4 men, 8 women and 4 machines take 5 days. Alternatively, 4 men, 1, women and 2 machines take 10 days to complete the job. Find the time taken by a women to complete the job (in says)
View SolutionBunty and Babli working together completed a job in 8 days. If Bunty worked twice efficiently as he actually did and Babli worked as efficiently as she actually did, the work would have been completed in 6 days. Find the time taken by Bunty to complete the job alone :
View Solution