Doubtnut Promotions Sticky

Note 1 : All the persons worked on the job X for whole number days.   Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.   If C worked on job Y with (5)/(4)times his given efficiency and was assisted by B every 3^(rd) day, then find the time taken by C to complete the job Y ?
Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
If C worked on job Y with 5 4 times his given efficiency and was assisted by B every 3 r d day, then find the time taken by C to complete the job Y ?

A

13 days

B

12 1 6 days

C

13 1 2 days

D

12 days

Video Solution
Text Solution
Verified by Experts

The correct Answer is:D


With new efficiency C will complete job in = 12 days
3 days work of C and 1 days work of B=1/3
Days required =9 days

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    10 persons can do a job in X days. If 20 persons with twice the efficiency can do the same job in 5 days, then find the value of X?
    A 40 B 15 C 20 D 30

    AB
    BC
    CA
    DD
  • Question 2 - Select One

    24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :

    A30
    B40
    C25
    D50
  • Question 3 - Select One

    A can do a job in 15 days, B in 10 days and C in 30 days. If A is helped by B and C on every third day, then the job will be completed in

    A613 days
    B813 days
    C8 days
    D9 days