Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
E worked on job 'Z' for 5 dyas and the remaining job was completed by A, B and D who worked on alternate days starting with A followed by B and D in thet order. Find the no. of days B worked for ?
2
4
9
3
The correct Answer is:D
Part of work completed by E=520=14
3 days work by (A+B+D)=110+112+118
=14+15+10180=43180
9 days work (3A+3B+3D)=129180
Remaining work =34−129180
=135−129180=6180=130
This will be done by A in =130×10=13 days
So B worked for 3 days.
Topper's Solved these Questions
Similar Questions
Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
If A,C abd E worked on job Z for 2 days each and the remaining job was done by B and D. if the ratio of no. days for which B and D worked is in ratio 20:21, then find the number of days for which B worked ?View Solution
Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
If the ratio of number of days for which B and D worked on job X is 4:3 , then find teh difference between of days for which B and D worked ?View Solution
Knowledge Check
- Question 1 - Select One
A can do a piece of work in 12 days. B can do the same work in 8 days and C can do the same job in 45th time required by both A and B. A and B work together for 3 days. Then C completes the job. How many complete days did C work?
A8B6C3DNone of these - Question 2 - Select One
A can complete 50% of a job in 9 days and B can complete 25% of the job in 9 days if they worked alone. If they worked together how much of the job (in %) can they complete in 9 days?
A80B90C75D100 - Question 3 - Select One
A can complete 50% of a job in 9 days and B can complete 25% of the job in 9 days if they worked alone. If they worked together how much of the job (in %) can they complete in 9 days?
A80B90C75D100
Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
A and C worked on job Y working alternatively for 10 days. B and D then worked together for 'x' day . if 136 of the job was still remained, then find the value of 'x' ?View Solution
Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
If C worked on job Y with 54times his given efficiency and was assisted by B every 3rd day, then find the time taken by C to complete the job Y ?View SolutionA,B,C,D and E are five persons to complete jobs X and Y. Line graph shows the data regarding the number of days taken by these persons to complete the job X and Y.
If A worked on job X for 5 days each and C worked for 3 days. the remaining job was done by E and D. If the ratio of the number of days for which D and E worked is in ratio 1:1, then find the number of days for which C, D and E worked?View SolutionA,B andC can do a job working alone in 12, 16 and 24 days, respectively.In how many days, they can do the job, if they worked together?
View SolutionTwo men A and B started a job in which A was thrice as good as B and therefore took 60 days less than B to finish the job. How many days will they take to finish the job, if they start working together?
View Solution