Doubtnut Promotions Sticky

Note 1 : All the persons worked on the job X for whole number days.   Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.    E worked on job 'Z' for 5 dyas and the remaining job was completed by A, B and D who worked on alternate days starting with A followed by B and D in thet order. Find the no. of days B worked for ?
Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
E worked on job 'Z' for 5 dyas and the remaining job was completed by A, B and D who worked on alternate days starting with A followed by B and D in thet order. Find the no. of days B worked for ?

A

2

B

4

C

9

D

3

Video Solution
Text Solution
Verified by Experts

The correct Answer is:D


Part of work completed by E=520=14
3 days work by (A+B+D)=110+112+118
=14+15+10180=43180
9 days work (3A+3B+3D)=129180
Remaining work =34129180
=135129180=6180=130
This will be done by A in =130×10=13 days
So B worked for 3 days.

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a piece of work in 12 days. B can do the same work in 8 days and C can do the same job in 45th time required by both A and B. A and B work together for 3 days. Then C completes the job. How many complete days did C work?

    A8
    B6
    C3
    DNone of these
  • Question 2 - Select One

    A can complete 50% of a job in 9 days and B can complete 25% of the job in 9 days if they worked alone. If they worked together how much of the job (in %) can they complete in 9 days?

    A80
    B90
    C75
    D100
  • Question 3 - Select One

    A can complete 50% of a job in 9 days and B can complete 25% of the job in 9 days if they worked alone. If they worked together how much of the job (in %) can they complete in 9 days?

    A80
    B90
    C75
    D100