Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
If the ratio of number of days for which B and D worked on job X is 4:3 , then find teh difference between of days for which B and D worked ?
2
3
1
4
The correct Answer is:C
Accrding to question,
210+412+315+3x18+220=1
⇒15+x3+11+15+x6+110=1
6x+10x+6+5x+330=1
15x15=30
x=1
Required difference =4x−3x
=4−3=1
Topper's Solved these Questions
Similar Questions
Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
If A,C abd E worked on job Z for 2 days each and the remaining job was done by B and D. if the ratio of no. days for which B and D worked is in ratio 20:21, then find the number of days for which B worked ?View Solution
Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
E worked on job 'Z' for 5 dyas and the remaining job was completed by A, B and D who worked on alternate days starting with A followed by B and D in thet order. Find the no. of days B worked for ?View Solution
Knowledge Check
- Question 1 - Select One
Three men and 5 women together can finish a job in 3 days. Working on the same job 3 women take 5 days more than the time required by 2 men. What is the ratio of efficiency of a man to a woman?
A2:1B3:2C5:2D4:1 - Question 2 - Select One
P and Q together can do a job in 6 days. Q and R can finish the same job in 607 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is.
A12B10C15D8
Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
A and C worked on job Y working alternatively for 10 days. B and D then worked together for 'x' day . if 136 of the job was still remained, then find the value of 'x' ?View Solution
Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
If C worked on job Y with 54times his given efficiency and was assisted by B every 3rd day, then find the time taken by C to complete the job Y ?View SolutionA,B,C,D and E are five persons to complete jobs X and Y. Line graph shows the data regarding the number of days taken by these persons to complete the job X and Y.
If A worked on job X for 5 days each and C worked for 3 days. the remaining job was done by E and D. If the ratio of the number of days for which D and E worked is in ratio 1:1, then find the number of days for which C, D and E worked?View SolutionA,B,C,D and E are five persons to complete jobs X and Y. Line graph shows the data regarding the number of days taken by these persons to complete the job X and Y.
If the ratio of the number of days for which D and C worked on job Y is 12:5 and completed the work then find the difference between number of days for which C and D worked.View SolutionA,B,C,D and E are five persons to complete jobs X and Y. Line graph shows the data regarding the number of days taken by these persons to complete the job X and Y.
If B worked on job Y with 4/9 times his work efficiency and assisted by D every 3rd day then find the number of days for which B and D worked to complete the job.View SolutionP and Q together can do a job in 6 days. Q and R can finish the same job in 60/7 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is
View Solution