Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
If A,C abd E worked on job Z for 2 days each and the remaining job was done by B and D. if the ratio of no. days for which B and D worked is in ratio 20:21, then find the number of days for which B worked ?
50 days
412 days
512 days
4 days
The correct Answer is:D
Work done by A,C and E on job Z in 2 days is-
=210+215+220
=12+8+660
=2660=1330
Remaaining work done by B and D in 20x and 21x
20x12+21x18=1730
60x+42x36=1730⇒102x=17×3630
x=630=15
Required days =20×15=4 days
Topper's Solved these Questions
Similar Questions
Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
E worked on job 'Z' for 5 dyas and the remaining job was completed by A, B and D who worked on alternate days starting with A followed by B and D in thet order. Find the no. of days B worked for ?View Solution
Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
If the ratio of number of days for which B and D worked on job X is 4:3 , then find teh difference between of days for which B and D worked ?View Solution
Knowledge Check
- Question 1 - Select One
If 12 men can do a job in 7 days, what fraction of the job can be done by one man in one day?
A114B712C184D172 - Question 2 - Select One
A and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?
A2 daysB3 daysC1 dayDNone of these - Question 3 - Select One
If A, B and C together do a job in 4 days, A and C together do the job in 4.5 days and B and C together do the job in 12 days then in how many days can C alone do the job?
A36B6C18D12
Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
A and C worked on job Y working alternatively for 10 days. B and D then worked together for 'x' day . if 136 of the job was still remained, then find the value of 'x' ?View Solution
Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
If C worked on job Y with 54times his given efficiency and was assisted by B every 3rd day, then find the time taken by C to complete the job Y ?View SolutionA,B,C,D and E are five persons to complete jobs X and Y. Line graph shows the data regarding the number of days taken by these persons to complete the job X and Y.
If A worked on job X for 5 days each and C worked for 3 days. the remaining job was done by E and D. If the ratio of the number of days for which D and E worked is in ratio 1:1, then find the number of days for which C, D and E worked?View SolutionA,B,C,D and E are five persons to complete jobs X and Y. Line graph shows the data regarding the number of days taken by these persons to complete the job X and Y.
If the ratio of the number of days for which D and C worked on job Y is 12:5 and completed the work then find the difference between number of days for which C and D worked.View SolutionTwo persons X and Y together can do a particular job in 36 days. If X's ability to do the work is twice that of Y, then find the number of days in which X and Y can do the work individually.
View Solution