Doubtnut Promotions Sticky

A and B can do a piece of work in 12 days, B and C in 15 days and C and A in 20 days. In how many days can they do it, all working together?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:10


To solve the problem, we need to find the individual work rates of A, B, and C based on the information given about their combined work rates. Here’s the step-by-step solution:

Step 1: Determine the work rates of A, B, and C
Let the total work be represented as 1 unit.

- A and B together can complete the work in 12 days.
- Work rate of A and B = 1/12 units of work per day.

- B and C together can complete the work in 15 days.
- Work rate of B and C = 1/15 units of work per day.

- C and A together can complete the work in 20 days.
- Work rate of C and A = 1/20 units of work per day.

Step 2: Set up equations based on work rates
Let the work rates of A, B, and C be represented as:
- Work rate of A = a
- Work rate of B = b
- Work rate of C = c

From the above information, we can set up the following equations:
1. a+b=112 (Equation 1)
2. b+c=115 (Equation 2)
3. c+a=120 (Equation 3)

Step 3: Solve the equations
To find the individual work rates, we can add all three equations together:
(a+b)+(b+c)+(c+a)=112+115+120
This simplifies to:
2a+2b+2c=112+115+120

Step 4: Calculate the right-hand side
To add the fractions, we need a common denominator. The least common multiple of 12, 15, and 20 is 60.
- Convert each fraction:
- 112=560
- 115=460
- 120=360

Now, add them:
560+460+360=1260=15

Step 5: Solve for a + b + c
Now we have:
2(a+b+c)=15
Dividing both sides by 2 gives:
a+b+c=110

Step 6: Calculate the total time for A, B, and C to work together
The combined work rate of A, B, and C is 110 units of work per day. Therefore, the time taken for all three to complete the work together is:
Time=Total WorkCombined Work Rate=1110=10 days

Final Answer
A, B, and C can complete the work together in 10 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can do a piece of work in 12 days, B and C in 15 days C and A in 20 days. In how many days can C alone do it ?

    A60
    B50
    C25
    D24
  • Question 2 - Select One

    A and B can do a piece of work in 12 days, B and C in 15 days and A and C in 20 days. In how many days can each alone do the work?

    A30,20,50
    B30,45,60
    C30,20,60
    D20,30,50
  • Question 3 - Select One

    A and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in :

    A60 days
    B120 days
    C80 days
    D30 days