If 12 carpenters, working 6 hours a day, can make 460 chairs in 24 days, how many chairs will 18 carpenters make in 36 days, each working 8 hours a day? 1260 b. 920 c. 1320 d. 1380
To solve the problem step by step, we will use the concept of work done, which is the product of the number of workers, the number of hours they work, and the number of days they work.
Step 1: Calculate the total work done by the first group of carpenters.
We know that:
- Number of carpenters = 12
- Hours worked per day = 6
- Days worked = 24
Total work done (in carpenter-hours) = Number of carpenters × Hours per day × Days
Total work=12×6×24
Calculating this gives:
Total work=12×6=72
72×24=1728 carpenter-hours
Step 2: Calculate the work done per chair.
From the problem, we know that these 12 carpenters made 460 chairs in that time.
So, the work done per chair is:
Work per chair=Total workNumber of chairs=1728460
Calculating this gives:
Work per chair≈3.75 carpenter-hours per chair
Step 3: Calculate the total work available for the second group of carpenters.
Now we need to calculate how much work 18 carpenters can do in 36 days, each working 8 hours a day.
- Number of carpenters = 18
- Hours worked per day = 8
- Days worked = 36
Total work done (in carpenter-hours) = Number of carpenters × Hours per day × Days
Total work=18×8×36
Calculating this gives:
Total work=18×8=144
144×36=5184 carpenter-hours
Step 4: Calculate the number of chairs that can be made by the second group.
Now we can find out how many chairs can be made with the total work available:
Number of chairs=Total workWork per chair=51843.75
Calculating this gives:
Number of chairs=1382.4
Since we cannot have a fraction of a chair, we round down to the nearest whole number, which is 1380.
Final Answer:
The number of chairs that 18 carpenters can make in 36 days, each working 8 hours a day is 1380.
We know that:
- Number of carpenters = 12
- Hours worked per day = 6
- Days worked = 24
Total work=12×6×24
Calculating this gives:
Total work=12×6=72
72×24=1728 carpenter-hours
From the problem, we know that these 12 carpenters made 460 chairs in that time.
So, the work done per chair is:
Work per chair=Total workNumber of chairs=1728460
Calculating this gives:
Work per chair≈3.75 carpenter-hours per chair
Now we need to calculate how much work 18 carpenters can do in 36 days, each working 8 hours a day.
- Number of carpenters = 18
- Hours worked per day = 8
- Days worked = 36
Total work=18×8×36
Calculating this gives:
Total work=18×8=144
144×36=5184 carpenter-hours
Now we can find out how many chairs can be made with the total work available:
Number of chairs=Total workWork per chair=51843.75
Calculating this gives:
Number of chairs=1382.4
Since we cannot have a fraction of a chair, we round down to the nearest whole number, which is 1380.
The number of chairs that 18 carpenters can make in 36 days, each working 8 hours a day is 1380.
Topper's Solved these Questions
Similar Questions
15 persons working 8 hours a day can complete a work in 21 days. How many days will 14 persons take to complete a work 112 times as great, if they work 6 hours a day?
View SolutionIf 5 men working 6 hours a day can reap a field in 20 days. In how many days will 15 men reap the field, working 8 hours a day ?
View Solution
Knowledge Check
If 12 carpenters working 6 hours a day can make 460 chairs in 240 days, then find the number of chairs made by 18 carpenters in 360 days each working 8 hours a day?
A92B132C138D126If 12 carpenters working 6 hours a day can make 460 chairs in 240 days, then find the number of chairs made by 18 carpenters in 360 days each working 8 hours a day?
A1. 1320B2. 1380C3. 1260D4. 920If 27 people, working 8 hours a day, can complete a task in 12 days, then in how many days will 18 people finish the task, working 9 hours a day?
A15 daysB16 daysC18 daysD20 days
18 men or 36 boys working 6 hours a day can plough a field in 24 days. In how many days will 24 men and 24 boys working 9 hours a day plough the same field?
View SolutionIf 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
View Solution18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?
View Solution18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?
View SolutionWorking 7 hours a day, 18 persons can complete a certain work in 32 days. In how many days would 14 persons complete the same work, working 8 hours a day ?
View Solution