Certain number of artisans can complete a shoe fabrication consignment in 16 days. 8 additional artisans had to be deployed for the same consignment and together they completed it in 4 days less than the earlier estimate. The number of artisans initially employed was 18 b. 20 c. 24 d. none of these
To solve the problem step by step, we will set up an equation based on the information provided.
Step 1: Define the variables
Let x be the initial number of artisans.
Step 2: Establish the relationship based on the problem
The initial number of artisans can complete the consignment in 16 days. Therefore, the total work done can be expressed as:
Total Work=x×16
Step 3: Consider the additional artisans
When 8 additional artisans are added, the total number of artisans becomes x+8. The problem states that they complete the work in 4 days less than the original estimate, which means they complete it in:
16−4=12 days
Thus, the total work done with the additional artisans can be expressed as:
Total Work=(x+8)×12
Step 4: Set up the equation
Since both expressions represent the same total work, we can set them equal to each other:
x×16=(x+8)×12
Step 5: Expand and simplify the equation
Expanding the right side gives:
16x=12x+96
Step 6: Rearrange the equation
Subtract 12x from both sides:
16x−12x=96
This simplifies to:
4x=96
Step 7: Solve for x
Dividing both sides by 4 gives:
x=964=24
Conclusion
The initial number of artisans employed was 24.
---
Let x be the initial number of artisans.
The initial number of artisans can complete the consignment in 16 days. Therefore, the total work done can be expressed as:
Total Work=x×16
When 8 additional artisans are added, the total number of artisans becomes x+8. The problem states that they complete the work in 4 days less than the original estimate, which means they complete it in:
16−4=12 days
Thus, the total work done with the additional artisans can be expressed as:
Total Work=(x+8)×12
Since both expressions represent the same total work, we can set them equal to each other:
x×16=(x+8)×12
Expanding the right side gives:
16x=12x+96
Subtract 12x from both sides:
16x−12x=96
This simplifies to:
4x=96
Dividing both sides by 4 gives:
x=964=24
The initial number of artisans employed was 24.
Topper's Solved these Questions
Similar Questions
B and C can complete a piece of work in 12 days, C and A can do it in 8 days. All the three can do it in 6 days. A and B together can complete It In
View SolutionA is thrice as efficient as B and hence completes a work in 40 days less than the number of days taken by B. What will be the number of days taken by both of them when working together?
View Solution
Knowledge Check
If A is twice as efficient as B, and A and B together can complete a work in 20 days, then find the number of days in which B can do the work alone.
(a)60 days
(b) 50 days
(c)30 days
(d)40 daysA60 daysB50 daysC30 daysD40 daysA and B can together complete a work in 16 days. B and C can together complete the same work in 24 days and A, B and C together can complete the work in 12 days. Find time taken by A and C to complete the work together.
(a)12 days
(b)14 days
(c)16 days
(d)18 daysA12 daysB14 daysC16 daysD18 daysA alone can complete a work in 10 days and B alone can complete the same work in 20 days. In how many days both 4 and B together can complete half of the total work?
A403 daysB203C103 daysD253 days
M can complete a work in 14 days less than the time taken by L. If both M and L together can complete the same work in 24 days, then in how many days M alone can complete the same work?
View SolutionA can complete a task in task in 16 days and B is 4 times faster than A. Find the part of work done by both A and B together in 1 day.
View SolutionA is thrice as efficient as B and hence completes a work in 40
days less than the number days taken by B. What will be
the number of days taken by both of them when working
together ?
View SolutionC alone can complete a work in 20 days and D alone can complete the same workin 30 days. In how many days C and D together can complete the same work?
View SolutionA, B and C can complete a work In 8 days. B alone can do it in 18 days and Calone can do it in 24 days. In how many days can A alone do the same work?
View Solution