Doubtnut Promotions Sticky

If 12 men can finish a work in 20 days , then find the number of days required to complete the same work by15 men .

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:16


To solve the problem of how many days 15 men will take to complete the same work that 12 men can finish in 20 days, we can follow these steps:

Step 1: Calculate the total work done in man-days
First, we need to determine the total work in terms of man-days. If 12 men can finish the work in 20 days, we can calculate the total work as follows:

Total Work=Number of Men×Number of Days=12 men×20 days=240 man-days

Step 2: Determine the work rate of 15 men
Next, we need to find out how many days it will take for 15 men to complete the same total work of 240 man-days. Let x be the number of days required for 15 men to finish the work. The equation can be set up as follows:

Total Work=Number of Men×Number of Days
240 man-days=15 men×x days

Step 3: Solve for x
Now, we can solve for x:

x=240 man-days15 men=16 days

Conclusion
Thus, 15 men will take 16 days to complete the same work.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?

    A21
    B20
    C24
    D22
  • Question 2 - Select One

    If 15 men can do a work in 48 days, then how many men will be required to complete the work in 30 days ?

    A,21
    B20
    C24
    D22
  • Question 3 - Select One

    24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :

    A32 men
    B30 men
    C35 men
    D36 men