If 12 men can finish a work in 20 days , then find the number of days required to complete the same work by15 men .
The correct Answer is:16
To solve the problem of how many days 15 men will take to complete the same work that 12 men can finish in 20 days, we can follow these steps:
Step 1: Calculate the total work done in man-days
First, we need to determine the total work in terms of man-days. If 12 men can finish the work in 20 days, we can calculate the total work as follows:
Total Work=Number of Men×Number of Days=12 men×20 days=240 man-days
Step 2: Determine the work rate of 15 men
Next, we need to find out how many days it will take for 15 men to complete the same total work of 240 man-days. Let x be the number of days required for 15 men to finish the work. The equation can be set up as follows:
Total Work=Number of Men×Number of Days
240 man-days=15 men×x days
Step 3: Solve for x
Now, we can solve for x:
x=240 man-days15 men=16 days
Conclusion
Thus, 15 men will take 16 days to complete the same work.
---
First, we need to determine the total work in terms of man-days. If 12 men can finish the work in 20 days, we can calculate the total work as follows:
Next, we need to find out how many days it will take for 15 men to complete the same total work of 240 man-days. Let x be the number of days required for 15 men to finish the work. The equation can be set up as follows:
240 man-days=15 men×x days
Now, we can solve for x:
Thus, 15 men will take 16 days to complete the same work.
Topper's Solved these Questions
- BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE BASE LEVEL QUESTION68videos
WORK AND TIME
- BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION16videos
WORK AND TIME
- BOOK - ARIHANT SSCCHAPTER - VOLUME AND SURFACE AREA EXERCISE - FAST TRACK PRACTICE111videos
VOLUME AND SURFACE AREA
- BOOK - ARIHANT SSCCHAPTER - WORK AND WAGES EXERCISE - EXERCISE (HIGHER SKILL LEVEL QUESTIONS)7videos
WORK AND WAGES
Similar Questions
If 5 men can do a piece of work in 10 days and 12 women can do the same work in 15 days, the number of days required to complete the work by 5 men and 6 women is
View Solution12 men can finish a piece of work in 25 days. The number of days in which the same piece of work can be done by 20 men, is (a) 10 days (b) 12 days (c) 15 days (d) 14 days
View Solution
Knowledge Check
- Question 1 - Select One
If 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?
A21B20C24D22 - Question 2 - Select One
If 15 men can do a work in 48 days, then how many men will be required to complete the work in 30 days ?
A,21B20C24D22 - Question 3 - Select One
24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
A32 menB30 menC35 menD36 men
If 35 men can finish a piece of work in 8 days, then the number of men who can do the same work in 10 days is :
View Solution450 man-days of work can be completed by a certain number of men in some days. If the number of people (men) are increased by 27, then the. number of day required to complete the same work is decreased- by 15. The number of days are required to complete the" three times work (than the previous/actual work) by 27 men?
View Solution450 man-days of work can be completed by a certain number of men in some days. If the number of people (men) are increased by 27, then the. number of day required to complete the same work is decreased- by 15. The number of days are required to complete the" three times work (than the previous/actual work) by 27 men?
View SolutionIf 8 men or 12 women can do a piece of work in 10 days, then what is the number of days required by 4 men and 4 women to finish the work ?
View Solution25 men and 15 women can complete the work in 12 days. They started working together and after 8 days, women left the work. Now 25 men complete the remaining work in 6 days. Find the time required to complete the work by only 15 women?
View Solution