Doubtnut Promotions Sticky

If 12 men can finish a work in 20 days , then find the number of days required to complete the same work by15 men .

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:16

|
Answer

Step by step video, text & image solution for If 12 men can finish a work in 20 days , then find the number of days required to complete the same work by15 men . by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Related Playlists


Similar Practice Problems

  • Question 1 - Select One

    If 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?

    A21
    B20
    C24
    D22
  • Question 1 - Select One

    If 15 men can do a work in 48 days, then how many men will be required to complete the work in 30 days ?

    A,21
    B20
    C24
    D22
  • Question 1 - Select One

    24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :

    A32 men
    B30 men
    C35 men
    D36 men
  • Question 1 - Select One

    If 35 men can finish a piece of work in 8 days, then the number of men who can do the same work in 10 days is :

    A38
    B28
    C19
    D17
  • Question 1 - Select One

    450 man-days of work can be completed by a certain number of men in some days. If the number of people (men) are increased by 27, then the. number of day required to complete the same work is decreased- by 15. The number of days are required to complete the" three times work (than the previous/actual work) by 27 men?

    A50
    B60
    C54
    D45
  • Question 1 - Select One

    450 man-days of work can be completed by a certain number of men in some days. If the number of people (men) are increased by 27, then the. number of day required to complete the same work is decreased- by 15. The number of days are required to complete the" three times work (than the previous/actual work) by 27 men?

    A50
    B60
    C54
    D45
  • Question 1 - Select One

    If 8 men or 12 women can do a piece of work in 10 days, then what is the number of days required by 4 men and 4 women to finish the work ?

    A12 days
    B22 days
    C10 days
    DNone of these
  • Question 1 - Select One

    25 men and 15 women can complete the work in 12 days. They started working together and after 8 days, women left the work. Now 25 men complete the remaining work in 6 days. Find the time required to complete the work by only 15 women?

    A36 days
    B88 days
    C94 days
    DNone of these

Similar Questions