A and B can do a piece of work in 40 days and 50 days , respectively. Both begin together but after a certain time , A leaves off . In this case B finished the remaining work in 20 days . After how many days did A leave ?
The correct Answer is:1313 days
To solve the problem step by step, we will first determine the work done by A and B, then calculate how long A worked before leaving.
Step 1: Determine the work rates of A and B
- A can complete the work in 40 days, so A's work rate is 140 of the work per day.
- B can complete the work in 50 days, so B's work rate is 150 of the work per day.
Hint: Work rate is calculated as the total work divided by the time taken to complete that work.
Step 2: Set up the equation for the total work done
Let A work for x days before leaving. In those x days, A and B work together. The amount of work done by A in x days is:
Work done by A=A′s rate×x=x40
The amount of work done by B in x days is:
Work done by B=B′s rate×x=x50
Thus, the total work done by A and B together in x days is:
Total work done in x days=x40+x50
Hint: To combine fractions, find a common denominator.
Step 3: Find a common denominator and simplify
The least common multiple of 40 and 50 is 200. Therefore, we can rewrite the work done as:
x40=5x200
x50=4x200
So, the total work done in x days is:
5x200+4x200=9x200
Hint: Combine the fractions by adding the numerators while keeping the common denominator.
Step 4: Calculate the remaining work done by B
After A leaves, B finishes the remaining work in 20 days. The amount of work done by B in 20 days is:
Work done by B in 20 days=B′s rate×20=2050=25
Hint: Remember that the total work is considered as 1 unit.
Step 5: Set up the equation for total work
The total work is 1 unit, so we can set up the equation:
Total work=Work done by A and B in x days+Work done by B in 20 days
1=9x200+25
Hint: Convert 25 to have a common denominator with 9x200.
Step 6: Solve for x
Convert 25 to a fraction with a denominator of 200:
25=80200
Now, substitute back into the equation:
1=9x200+80200
1=9x+80200
Multiply both sides by 200:
200=9x+80
Now, isolate x:
9x=200−80
9x=120
x=1209=403
Step 7: Convert x into days
To convert 403 into days:
403=1313 days
Final Answer
A leaves after 1313 days.
---
- A can complete the work in 40 days, so A's work rate is 140 of the work per day.
- B can complete the work in 50 days, so B's work rate is 150 of the work per day.
Let A work for x days before leaving. In those x days, A and B work together. The amount of work done by A in x days is:
Work done by A=A′s rate×x=x40
Work done by B=B′s rate×x=x50
Total work done in x days=x40+x50
The least common multiple of 40 and 50 is 200. Therefore, we can rewrite the work done as:
x40=5x200
x50=4x200
5x200+4x200=9x200
After A leaves, B finishes the remaining work in 20 days. The amount of work done by B in 20 days is:
Work done by B in 20 days=B′s rate×20=2050=25
The total work is 1 unit, so we can set up the equation:
Total work=Work done by A and B in x days+Work done by B in 20 days
1=9x200+25
Convert 25 to a fraction with a denominator of 200:
25=80200
1=9x200+80200
1=9x+80200
200=9x+80
9x=200−80
9x=120
x=1209=403
To convert 403 into days:
403=1313 days
A leaves after 1313 days.
Topper's Solved these Questions
- WORK AND TIME BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE BASE LEVEL QUESTION
68 Videos
- WORK AND TIME BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION
16 Videos
- VOLUME AND SURFACE AREA BOOK - ARIHANT SSCCHAPTER - VOLUME AND SURFACE AREA EXERCISE - FAST TRACK PRACTICE
111 Videos
- WORK AND WAGES BOOK - ARIHANT SSCCHAPTER - WORK AND WAGES EXERCISE - EXERCISE (HIGHER SKILL LEVEL QUESTIONS)
7 Videos
Similar Questions
A and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View SolutionA and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View Solution
Knowledge Check
A and B can do a piece of work in 60 days and 75 days, respectively. Both begin together but after a certain time A leaves off . In such case B finishes the remaining work in 30 days . After how many days did A leave ?
A25 daysB21 daysC20 daysD24 daysA and B can do a piece of work in 30 and 36 days respectively. They began the work together but A leaves after some days and B finished the remaining wrok in 25 days. After how many days did A leave?
A5 daysB10 daysC11 daysD6 daysA and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?
A2 daysB3 daysC1 dayDNone of these
A and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave?
View SolutionA and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave? 759days b. 8 days c. 9 days d. 1425days
View Solution