Doubtnut Promotions Sticky

Kavita, Babita and Samita started a work. 5 days later Samita left the work and Babita left the work after working 8 days. In how many more days Kavita would have completed the rest work if they take 20, 60 and 30 days individually to finish a work?

A

4

B

5

C

6

D

8

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will follow the outlined approach:

Step 1: Determine the work rates (efficiencies) of Kavita, Babita, and Samita.
- Kavita takes 20 days to complete the work, so her work rate is:
Efficiency of Kavita=120
- Babita takes 60 days to complete the work, so her work rate is:
Efficiency of Babita=160
- Samita takes 30 days to complete the work, so her work rate is:
Efficiency of Samita=130

Step 2: Calculate the total work done by each person during their respective working days.
- Samita works for 5 days:
Work done by Samita=5×130=530=16
- Babita works for 8 days:
Work done by Babita=8×160=860=215

Step 3: Calculate the total work done by Kavita, Babita, and Samita together.
- The total work done by Samita and Babita together in the first 8 days is:
Total work done=16+215
- To add these fractions, we need a common denominator. The LCM of 6 and 15 is 30.
- Convert 16 to 530
- Convert 215 to 430

So,
Total work done=530+430=930=310

Step 4: Calculate the remaining work.
- The total work is considered as 1 unit, so the remaining work after 8 days is:
Remaining work=1310=710

Step 5: Determine how long it will take Kavita to complete the remaining work alone.
- Kavita's efficiency is 120, so the time t taken by Kavita to complete 710 of the work is given by:
Time=Remaining workEfficiency of Kavita=710120=710×20=14 days

Step 6: Determine how long it would take all three working together to complete the work.
- The combined efficiency of Kavita, Babita, and Samita is:
Combined efficiency=120+160+130
- The LCM of 20, 60, and 30 is 60.
- Convert 120 to 360
- Convert 160 to 160
- Convert 130 to 260

So,
Combined efficiency=360+160+260=660=110
- This means they can complete the work together in 10 days.

Step 7: Calculate the difference in time taken by Kavita and the combined group.
- Kavita takes 14 days, and the group takes 10 days, so the difference is:
Difference=1410=4 days

Final Answer:
Kavita would take 4 more days to complete the rest of the work alone.

---

|
Updated on:18/9/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work ?

    A203 days
    B253 days
    C6 days
    D5 days
  • Question 2 - Select One

    A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?

    A38
    B51
    C46
    D62
  • Question 3 - Select One

    Vinay and Varma can do a work in 30 days and 60 days respectively. If they work on alternate days beginning with Vinay, in how many days will the work be completed?

    A45
    B35
    C40
    D50