150 workers were engaged to finish a job in a certain number of days. 4 workers dropped out on second day, 4 more workers dropped out on third day and so on. Solution in Bengali
The correct Answer is:25 days
Step by step video, text & image solution for 150 workers were engaged to finish a job in a certain number of days. 4 workers dropped out on second day, 4 more workers dropped out on third day and so on. by Maths experts to help you in doubts & scoring excellent marks in Class 11 exams.
Topper's Solved these Questions
- BOOK - NCERT BANGLISHCHAPTER - SEQUENCES AND SERIESEXERCISE - EXERCISE 9.410videos
SEQUENCES AND SERIES
- BOOK - NCERT BANGLISHCHAPTER - RELATIONS AND FUNCTIONSEXERCISE - Miscellaneous Exercise on Chapter 212videos
RELATIONS AND FUNCTIONS
- BOOK - NCERT BANGLISHCHAPTER - SETSEXERCISE - MISCELLANEOUS EXERCISE ON CHAPTER 126videos
SETS
Similar Questions
Find the sum to n terms of each of the series in
1×2+2×3+3×4+4×5+....04:08View SolutionThe relation f is defined by f(x)={x20≤x≤33x3≤x≤10
The relation g is defined by g(x)={x20≤x≤23x2≤x≤10
Show that f is a function and g is not a function.07:28View SolutionDecide, among the following sets, which sets are subsets of one and another:
A = { x:x∈Randx satisfy x2–8x+12=0 },
B={2,4,6},C={2,4,6,8,...},D={6}.08:46View SolutionIn a factory, 150 workers were engaged to finish a piece of work in a certain number of days. However, if 4 workers are dropped everyday, except the first day, it will take 8 more days to finish the work. Find the number of days in which the work was to be completed.
06:38View Solution150 workers were engaged to finish a job in a certain number of days.4 workers dropped out on second day,4 more workers dropped out on the third day and so on.It took 8 more days to finish the work.Find the number of days in which the work was complete.
View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.
02:01View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four wirkers dropped from the work in the second day. Four workers dropped in third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed.
[ Let the no. of days to finish the work is 'x' then
150x=x+82[2×150+(x+8−1)(−4)]06:22View Solution150 workers were engaged to finish a job in a certain number of days. 4 workers dropped out on second day, 4 more workers dropped out on third day and so on.
06:07View SolutionIf they are in G.P.Write next one terms.
a,2a, 3a, 4a,......08:23View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped from the work on the second day. Four workers dropped on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed. [Let the no.of days to finish the work is 'x' then
150x=x+82[2×150+(x+8−1)(−4)]08:23View Solution150 workers were engaged to finish a job in a certain number of days. 4 workers dropped out on second day, 4 more workers dropped out on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed.
10:57View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped from the work on the second day. Four workers dropped on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed. [Let the no.of days to finish the work is 'r' then
150x=x+82[2×150+(x+8−1)(−4)]04:58View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped from the work on the second day. Four workers dropped on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed. [Let the no.of days to finish the work is 'r' then
150x=x+82[2×150+(x+8−1)(−4)]04:01View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped from the work on the second day. Four workers dropped on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed. [Let the no.of days to finish the work is 'r' then
150x=x+82[2×150+(x+8−1)(−4)]05:11View Solution150 workers were engaged to finish a job in a certain number of days. 4 workers dropped out on second day, 4 more workers dropped out on third day and so on.
06:02View Solution