15. A contractor took a contract to complete a work in 60 days, He employed 50 laborers, after 40 days the work was half done. Now How many more laborers should he increase so that the work is completed on time Go (1) 40 laborers (2) 50 laborers (3) 55 laborers (4) 60 laborers
Step by step video & image solution for 15. A contractor took a contract to complete a work in 60 days, He employed 50 laborers, after 40 days the work was half done. Now How many more laborers should he increase so that the work is completed on time Go (1) 40 laborers (2) 50 laborers (3) 55 laborers (4) 60 laborers by Maths experts to help you in doubts & scoring excellent marks in Class 6 exams.
Similar Questions
A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work is completed How many men should be increased so that the work will be completed in 25 days less than the scheduled time
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work may finish in time ?
View Solution
Knowledge Check
- Question 1 - Select One
A contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?
A50B40C30D10 - Question 2 - Select One
A contractor wants to complete a project in 90 days and he employed 60 workmen. After 60 days 3/4 of the work is completed. Then how many persons should he remove so that the project will be completed in stipulated time?
A15B20C25D30 - Question 3 - Select One
A contractor undertakes to make a mall in 60 days and he
employs 30 men. After 30 days it is found that only one-
third of the work is completed. How many extre men should
he employ so that the work is completed on time?A20 menB25 menC30 menD40 men
A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?
View SolutionA contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only onethird of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 23 of the work. How many men can be discharge now so that the work may finish in time?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that they had already done 23 of the work.
How many men can be discharged now so that the work may finish in time?View SolutionA contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
View Solution