Doubtnut Promotions Sticky

15. A contractor took a contract to complete a work in 60 days, He employed 50 laborers, after 40 days the work was half done. Now How many more laborers should he increase so that the work is completed on time Go (1) 40 laborers (2) 50 laborers (3) 55 laborers (4) 60 laborers

Video Solution
|
Answer

Step by step video & image solution for 15. A contractor took a contract to complete a work in 60 days, He employed 50 laborers, after 40 days the work was half done. Now How many more laborers should he increase so that the work is completed on time Go (1) 40 laborers (2) 50 laborers (3) 55 laborers (4) 60 laborers by Maths experts to help you in doubts & scoring excellent marks in Class 6 exams.

Updated on:21/07/2023

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?

    A50
    B40
    C30
    D10
  • Question 2 - Select One

    A contractor wants to complete a project in 90 days and he employed 60 workmen. After 60 days 3/4 of the work is completed. Then how many persons should he remove so that the project will be completed in stipulated time?

    A15
    B20
    C25
    D30
  • Question 3 - Select One

    A contractor undertakes to make a mall in 60 days and he
    employs 30 men. After 30 days it is found that only one-
    third of the work is completed. How many extre men should
    he employ so that the work is completed on time?

    A20 men
    B25 men
    C30 men
    D40 men