Doubtnut Promotions Sticky

A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?

A

70

B

75

C

80

D

85

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:75


To solve the problem step by step, we will follow the reasoning laid out in the video transcript.

1. Understanding the Problem:
The contractor has 40 days to complete the road with 25 men. After 24 days, only one-third of the road is completed. The contractor wants to finish the remaining work 4 days earlier than the original schedule.

2. Calculate the Total Work:
Let the total work required to complete the road be represented as W. Since one-third of the road is completed in 24 days, the remaining work is:
Wremaining=W13W=23W

3. Determine the Remaining Time:
Since the contractor originally planned to complete the work in 40 days and has already spent 24 days, he has:
4024=16 days remaining
However, he wants to finish 4 days earlier, so the new time to complete the remaining work is:
164=12 days

4. Calculate the Work Rate:
The work done by 25 men in 24 days is:
Work done=25 men×24 days=600 man-days
Since this represents one-third of the total work:
W=3×600=1800 man-days

5. Calculate Remaining Work:
The remaining work is:
Wremaining=23W=23×1800=1200 man-days

6. Determine Required Work Rate:
To complete the remaining work of 1200 man-days in 12 days, the required number of men M can be calculated as:
M×12=1200M=120012=100 men

7. Calculate Extra Men Needed:
The contractor initially had 25 men. Therefore, the number of extra men x needed is:
x=M25=10025=75

Final Answer:
The contractor needs to employ 75 extra men to complete the work 4 days earlier.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A contractor undertakes to make a mall in 60 days and he
    employs 30 men. After 30 days it is found that only one-
    third of the work is completed. How many extre men should
    he employ so that the work is completed on time?

    A20 men
    B25 men
    C30 men
    D40 men
  • Question 2 - Select One

    A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?

    A20
    B30
    C15
    D45
  • Question 3 - Select One

    A contractor undertakes to built a walls in 50 days. He employs 50 peoples for the same. However after 25 days he finds that only 40% of the work is complete. How many more man need to be employed to complete the work in time?

    Aa) 25
    Bb) 30
    Cc) 35
    Dd) 20