A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
70
75
80
85
The correct Answer is:75
To solve the problem step by step, we will follow the reasoning laid out in the video transcript.
1. Understanding the Problem:
The contractor has 40 days to complete the road with 25 men. After 24 days, only one-third of the road is completed. The contractor wants to finish the remaining work 4 days earlier than the original schedule.
2. Calculate the Total Work:
Let the total work required to complete the road be represented as W. Since one-third of the road is completed in 24 days, the remaining work is:
Wremaining=W−13W=23W
3. Determine the Remaining Time:
Since the contractor originally planned to complete the work in 40 days and has already spent 24 days, he has:
40−24=16 days remaining
However, he wants to finish 4 days earlier, so the new time to complete the remaining work is:
16−4=12 days
4. Calculate the Work Rate:
The work done by 25 men in 24 days is:
Work done=25 men×24 days=600 man-days
Since this represents one-third of the total work:
W=3×600=1800 man-days
5. Calculate Remaining Work:
The remaining work is:
Wremaining=23W=23×1800=1200 man-days
6. Determine Required Work Rate:
To complete the remaining work of 1200 man-days in 12 days, the required number of men M can be calculated as:
M×12=1200⟹M=120012=100 men
7. Calculate Extra Men Needed:
The contractor initially had 25 men. Therefore, the number of extra men x needed is:
x=M−25=100−25=75
Final Answer:
The contractor needs to employ 75 extra men to complete the work 4 days earlier.
---
The contractor has 40 days to complete the road with 25 men. After 24 days, only one-third of the road is completed. The contractor wants to finish the remaining work 4 days earlier than the original schedule.
Let the total work required to complete the road be represented as W. Since one-third of the road is completed in 24 days, the remaining work is:
Wremaining=W−13W=23W
Since the contractor originally planned to complete the work in 40 days and has already spent 24 days, he has:
40−24=16 days remaining
However, he wants to finish 4 days earlier, so the new time to complete the remaining work is:
16−4=12 days
The work done by 25 men in 24 days is:
Work done=25 men×24 days=600 man-days
Since this represents one-third of the total work:
W=3×600=1800 man-days
The remaining work is:
Wremaining=23W=23×1800=1200 man-days
To complete the remaining work of 1200 man-days in 12 days, the required number of men M can be calculated as:
M×12=1200⟹M=120012=100 men
The contractor initially had 25 men. Therefore, the number of extra men x needed is:
x=M−25=100−25=75
The contractor needs to employ 75 extra men to complete the work 4 days earlier.
Topper's Solved these Questions
Similar Questions
A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 23 of the work. How many men can be discharge now so that the work may finish in time?
View Solution
Knowledge Check
- Question 1 - Select One
A contractor undertakes to make a mall in 60 days and he
employs 30 men. After 30 days it is found that only one-
third of the work is completed. How many extre men should
he employ so that the work is completed on time?A20 menB25 menC30 menD40 men - Question 2 - Select One
A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?
A20B30C15D45 - Question 3 - Select One
A contractor undertakes to built a walls in 50 days. He employs 50 peoples for the same. However after 25 days he finds that only 40% of the work is complete. How many more man need to be employed to complete the work in time?
Aa) 25Bb) 30Cc) 35Dd) 20
A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work may finish in time ?
View Solution40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?
View SolutionA contractor wants to complete a project in 90 days and he employed 60 workmen. After 60 days 3/4 of the work is completed. Then how many persons should he remove so that the project will be completed in stipulated time?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that they had already done 23 of the work.
How many men can be discharged now so that the work may finish in time?View Solution20 men complete one-third of a work in 20 days. How may more men should be employed to finish the rest of th ework in 25 more days ?
View Solution