A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only onethird of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
100
60
75
None of these
The correct Answer is:C
To solve the problem step by step, we will follow a structured approach:
Step 1: Understand the Problem
The contractor has 40 days to complete a road with 25 men. After 24 days, only one-third of the road is completed. He needs to finish the remaining two-thirds of the road in 36 days (4 days earlier than planned).
Hint: Break down the total work into fractions to understand how much is left and how much time is available.
Step 2: Calculate the Work Done
In 24 days, 25 men completed one-third of the road.
Let the total work be represented as W.
- Work done in 24 days = 13W
Hint: Use the formula for work done: Work = Number of men × Number of days.
Step 3: Calculate the Remaining Work
The remaining work is:
- Remaining work = Total work - Work done = W−13W=23W
Hint: Always check how much work is left after a certain period.
Step 4: Determine the Time Left
The contractor now has 36 days to complete the remaining work.
Hint: Keep track of the time constraints to ensure the work can be completed on schedule.
Step 5: Set Up the Equation
Let x be the number of extra men to be employed. The total number of men after hiring extra men will be 25+x.
The equation using the work formula is:
(25+x)×36=23W
From the first part, we know:
25×24=13W⟹W=25×24×3=1800
Now substitute W into the equation:
(25+x)×36=23×1800
Hint: Substitute known values to simplify the equation.
Step 6: Simplify the Equation
Calculate 23×1800:
23×1800=1200
So the equation becomes:
(25+x)×36=1200
Hint: Always simplify your calculations to make the problem easier to solve.
Step 7: Solve for x
Now divide both sides by 36:
25+x=120036=33.33
Now, subtract 25 from both sides:
x=33.33−25=8.33
Since x must be a whole number, we round up to the nearest whole number:
x=9
Hint: When dealing with people, always round up to ensure you have enough workers.
Step 8: Conclusion
The contractor needs to hire 9 extra men to complete the work in 36 days.
Final Answer: The contractor should employ 9 extra men.
The contractor has 40 days to complete a road with 25 men. After 24 days, only one-third of the road is completed. He needs to finish the remaining two-thirds of the road in 36 days (4 days earlier than planned).
In 24 days, 25 men completed one-third of the road.
- Work done in 24 days = 13W
The remaining work is:
- Remaining work = Total work - Work done = W−13W=23W
The contractor now has 36 days to complete the remaining work.
Let x be the number of extra men to be employed. The total number of men after hiring extra men will be 25+x.
(25+x)×36=23W
25×24=13W⟹W=25×24×3=1800
(25+x)×36=23×1800
Calculate 23×1800:
23×1800=1200
So the equation becomes:
(25+x)×36=1200
Now divide both sides by 36:
25+x=120036=33.33
Now, subtract 25 from both sides:
x=33.33−25=8.33
x=9
The contractor needs to hire 9 extra men to complete the work in 36 days.
Similar Questions
A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 23 of the work. How many men can be discharge now so that the work may finish in time?
View Solution
Knowledge Check
- Question 1 - Select One
A contractor undertakes to make a mall in 60 days and he
employs 30 men. After 30 days it is found that only one-
third of the work is completed. How many extre men should
he employ so that the work is completed on time?A20 menB25 menC30 menD40 men - Question 2 - Select One
A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?
A20B30C15D45 - Question 3 - Select One
A contractor undertakes to built a walls in 50 days. He employs 50 peoples for the same. However after 25 days he finds that only 40% of the work is complete. How many more man need to be employed to complete the work in time?
Aa) 25Bb) 30Cc) 35Dd) 20
A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work may finish in time ?
View SolutionA contractor wants to complete a project in 90 days and he employed 60 workmen. After 60 days 3/4 of the work is completed. Then how many persons should he remove so that the project will be completed in stipulated time?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that they had already done 23 of the work.
How many men can be discharged now so that the work may finish in time?View Solution40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?
View SolutionA contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done 35 part of the work, the number of men he can withdraw so that the work may still be finished in time is :
View Solution