The number of days required by A, B and C to work individually is 6, 12 and 8 respectively. They started a work doing it alternatively. If A has started then followed by B and so on, how many days are needed to complete the whole work?
In the
above question if the order of working days be as B,C,A,B,C,A…(starting with B and followed by C and A respectively), then in how many days the work will he completed?
734
8
814
9
The correct Answer is:C
Step by step video, text & image solution for The number of days required by A, B and C to work individually is 6, 12 and 8 respectively. They started a work doing it alternatively. If A has started then followed by B and so on, how many days are needed to complete the whole work?In the above question if the order of working days be as B,C,A,B,C,A…(starting with B and followed by C and A respectively), then in how many days the work will he completed? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Updated on:21/07/2023Topper's Solved these Questions
Similar Questions
A and B can do a piece of work in 6 days and 9 days respectively, they work on alternative days starting with A on the first day. In how many days will the work be completed ?
View SolutionA, B and C can do piece of work in 18,24 and 36 days respectively . They work alternately , first day C, second day B and third day A, fourth day C and so on. How many days will be needed to complete the work like this way?
View Solution
Knowledge Check
The number of days required by A, B and C to work individually is 6, 12 and 8 respectively. They started a work doing it alternatively. If A has started then followed by B and so on, how many days are needed to complete the whole work?
A8B7.5C8.5D912The number of days required by A, B and C to work individually is 6, 12 and 8 respectively. They started a work doing it alternatively. If A has started then followed by B and so on, how many days are needed to complete the whole work?
In the above question if the order of working days be as B,C,A,B,C,A…(starting with B and followed by C and A respectively), then in how many days the work will he completed?A734B8C814D9The number of days required by A, B and C to work individually is 6, 12 and 8 respectively. They started a work doing it alternatively. If A has started then followed by B and so on, how many days are needed to complete the whole work?
In the above question if the order of working days be as B,C,A,B,C,A…(starting with B and followed by C and A respectively), then in how many days the work will he completed?A734B8C814D9
A,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?
View SolutionA,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?
View SolutionA,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?
View SolutionA can do a work in 6 days, B can do it in 8 days and C can complete it in 12 days. If A starts the work and they work in alternatively, then in how many days, the work will be completed?
View SolutionA, b and C can alone complete a work in 10, 12 and 15 days
respectively. A and C started the work and after working for
4 days, A left and B joined. In how many days the total work
was completed ?
View Solution