Colonel, Major and General started a work together fort ₹ 816. Colonel and Major did 817 of the total work, while Major and General together did (1217) of the whole work. What is the amount of the least efficient person?
₹ 256
₹ 144
₹ 85
can’t be determined
The correct Answer is:B
Step by step video, text & image solution for Colonel, Major and General started a work together fort ₹ 816. Colonel and Major did 8/17 of the total work, while Major and General together did (12/17) of the whole work. What is the amount of the least efficient person? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Related Playlists
Similar Questions
Colonel, Major and General started a work together for Rs. 816. Colonel and Major did 817 of the total work, while Major and General together did 1217of the whole work. What is the amount of the least efficient person?
View SolutionIf A takes 4/5 days as B takes and working together they require 203 days to complete the whole work What is the efficiency of B ?
View SolutionIf A takes 4/5 days as B-takes and working together they require 203 days to complete the whole work. What is the efficiency of B ?
View Solution15 men can complete a work in 12 days they start the work together . In how many days the total work will be finished when.
After 4 days 5 more men join the work.View Solution15 men can complete a work in 12 days they start the work together . In how many days the total work will be finished when.
After 4 days 5 men left the work .View SolutionA and B undertook a work for Rs. 2200. A alone can do the work in 10 days and B alone can do the same work in 12 days. If they work together, what will be the difference( in Rs.) in the amount they receive?
View SolutionA and B undertook a work for Rs. 2200. A alone can do the work in 10 days and B alone can do the same work in 12 days. If they work together, what will be the difference( in Rs.) in the amount they receive?
View SolutionBoston, Churchill and David are three workers, employed by a contractor. They completed the whole work in 10 days. Initially all of them worked together, but the last 60% of the work was completed by only Churchill and David together. Boston worked with Churchill and David only for initial two days then he left the work due to his poor health. Also Churchill takes 20% less time to finish the work alone than that of David working alone. If they were paid ₹ 3000 for the entire work, then what is the share of least efficient person?
View SolutionBoston, Churchill and David are three workers, employed by a contractor. They completed the whole work in 10 days. Initially all of them worked together, but the last 60% of the work was completed by only Churchill and David together. Boston worked with Churchill and David only for initial two days then he left the work due to his poor health. Also Churchill takes 20% less time to finish the work alone than that of David working alone. If they were paid ₹ 3000 for the entire work, then what is the share of least efficient person?
View SolutionEach of A, B, C and D need a umique
time to do a certain work. A can do the work in x days and B can
do the work in 2x days. A started the work and do it for 2229 days
then he is replaced by B and B completed remaining work in same
time as C and D together can complete the whole work.
The ratio of the efficiency of C and D is 4:5. If C and D work for
alternative days starting form C then they can do the total work
in 4412 days.View Solution