A certain-job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and remaining men did the job in 32 days. The original number of men in the group was :
32
36
42
40
The correct Answer is:A
To solve the problem step by step, we will use the relationship between the number of men, the number of days they work, and the total work done.
Let's denote:
- M = original number of men
- D1 = original number of days to complete the job = 20 days
- D2 = actual number of days taken to complete the job = 32 days
- W = total work (which remains constant)
Step 1: Set up the equation for work done
The work done can be expressed in terms of men and days:
M×D1=W
This means:
M×20=W
Step 2: Determine the number of men who actually worked
Since 12 men did not turn up, the number of men who actually worked is:
M−12
Step 3: Set up the equation for the actual work done
The actual work done by the remaining men can also be expressed as:
(M−12)×D2=W
This means:
(M−12)×32=W
Step 4: Set the two equations for work equal to each other
Since both expressions equal the total work W, we can set them equal:
M×20=(M−12)×32
Step 5: Expand and simplify the equation
Expanding the right side:
M×20=M×32−12×32
This simplifies to:
20M=32M−384
Step 6: Rearrange the equation to isolate M
Now, we rearrange the equation:
32M−20M=384
This simplifies to:
12M=384
Step 7: Solve for M
Dividing both sides by 12 gives:
M=38412=32
Conclusion
The original number of men in the group was 32.
---
- M = original number of men
- D1 = original number of days to complete the job = 20 days
- D2 = actual number of days taken to complete the job = 32 days
- W = total work (which remains constant)
The work done can be expressed in terms of men and days:
M×D1=W
This means:
M×20=W
Since 12 men did not turn up, the number of men who actually worked is:
M−12
The actual work done by the remaining men can also be expressed as:
(M−12)×D2=W
This means:
(M−12)×32=W
Since both expressions equal the total work W, we can set them equal:
M×20=(M−12)×32
Expanding the right side:
M×20=M×32−12×32
This simplifies to:
20M=32M−384
Now, we rearrange the equation:
32M−20M=384
This simplifies to:
12M=384
Dividing both sides by 12 gives:
M=38412=32
The original number of men in the group was 32.
Topper's Solved these Questions
Similar Questions
Knowledge Check
A certain job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and the remaining men did the job in 32 days. The original number of men in the group was :
A32B36C42D40Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was
A24B20C16D18Some carpenters promised to do a job in 15 days but 3 of them were absent and remaining did the job in 20 days. What was the original number of carpenters?
A10B15C12D14
A certain numner of men agreed to do a work in 20 days. 5 men did come for work. Others completed the work in 40 days. Find the number of men who had agreed to do the work originally.
View Solution24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
View SolutionA certain number of men can do a plece of work in 60 days. If there were 6 men more, the work can be finished 20 days earlier. The number of men working is :
View SolutionIf m men can do a work in r days, then the number of days taken by (m+n) men do it is :
View SolutionA group of men decided to do a job in 8 days. But since 10 men dropped out every day, the job got completed at the end of the 12th day. How many men were there at the beginning?
View Solution