A certain-job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and remaining men did the job in 32 days. The original number of men in the group was :

A

32

B

36

C

42

D

40

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will use the relationship between the number of men, the number of days they work, and the total work done.

Let's denote:
- M = original number of men
- D1 = original number of days to complete the job = 20 days
- D2 = actual number of days taken to complete the job = 32 days
- W = total work (which remains constant)

Step 1: Set up the equation for work done
The work done can be expressed in terms of men and days:
M×D1=W
This means:
M×20=W

Step 2: Determine the number of men who actually worked
Since 12 men did not turn up, the number of men who actually worked is:
M12

Step 3: Set up the equation for the actual work done
The actual work done by the remaining men can also be expressed as:
(M12)×D2=W
This means:
(M12)×32=W

Step 4: Set the two equations for work equal to each other
Since both expressions equal the total work W, we can set them equal:
M×20=(M12)×32

Step 5: Expand and simplify the equation
Expanding the right side:
M×20=M×3212×32
This simplifies to:
20M=32M384

Step 6: Rearrange the equation to isolate M
Now, we rearrange the equation:
32M20M=384
This simplifies to:
12M=384

Step 7: Solve for M
Dividing both sides by 12 gives:
M=38412=32

Conclusion
The original number of men in the group was 32.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A certain job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and the remaining men did the job in 32 days. The original number of men in the group was :

    A32
    B36
    C42
    D40
  • Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was

    A24
    B20
    C16
    D18
  • Some carpenters promised to do a job in 15 days but 3 of them were absent and remaining did the job in 20 days. What was the original number of carpenters?

    A10
    B15
    C12
    D14