Doubtnut Promotions Sticky

Each of A, B, C and D need a umique
time to do a certain work. A can do the work in x days and B can
do the work in 2x days. A started the work and do it for 2229 days
then he is replaced by B and B completed remaining work in same
time as C and D together can complete the whole work.
The ratio of the efficiency of C and D is 4:5. If C and D work for
alternative days starting form C then they can do the total work
in 4412 days.

A

66(2/3)

B

33(1/3)

C

16(2/3)

D

14(2/7)

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:(a)


To solve the problem step by step, let's break down the information given and calculate accordingly.

Step 1: Understand the Work Done by A
A can complete the work in x days. Therefore, A's work rate (efficiency) is:
Efficiency of A=1x (work per day)

Step 2: Calculate Work Done by A in 22 and 29 Days
A works for 2229 days. We convert this to an improper fraction:
2229=2009 days
The work done by A in this time is:
Work done by A=Efficiency of A×Time=1x×2009=2009x

Step 3: Remaining Work
Since the total work is 1 (whole work), the remaining work after A's contribution is:
Remaining Work=12009x=9x2009x

Step 4: Work Done by B
B can complete the work in 2x days, so B's efficiency is:
Efficiency of B=12x
Let t be the time taken by B to complete the remaining work. The work done by B can be expressed as:
Work done by B=Efficiency of B×t=12x×t
Setting this equal to the remaining work:
12x×t=9x2009x

Step 5: Time Taken by C and D Together
It is given that B completes the remaining work in the same time as C and D together can complete the whole work. The efficiency ratio of C and D is 4:5. Let the efficiencies of C and D be 4y and 5y respectively. Thus, their combined efficiency is:
Efficiency of C and D=4y+5y=9y
The time taken by C and D to complete the whole work is:
Time taken by C and D=19y

Step 6: Work Done by C and D in Alternative Days
C and D work alternately starting from C and can complete the total work in 4412 days:
4412=892 days
In 4412 days, they complete the work, which means:
Total Work=Total Days×Combined Efficiency=892×9y=801y2
Setting this equal to 1 (total work):
801y2=1y=2801

Step 7: Substitute Back to Find x
Now we can substitute y back into the equations. The efficiency of C and D becomes:
Efficiency of C=4y=8801,Efficiency of D=5y=10801
Now, we can find t using the equation from Step 4:
12x×t=9x2009x
Since t=19y:
12x×19y=9x2009x
Substituting y:
12x×80118=9x2009x
Cross-multiplying and solving for x:
80136x=9x2009x
Solving this will lead to:
x=60018=33.33 days (or 3313 days)

Final Answer
Thus, the unique time x for A to complete the work is:
3313 days

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do 25 of a work in 6 days and B can do 23 of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:

    A12 days
    B9 days
    C10 days
    D8 days
  • Question 2 - Select One

    A can do 45 of a work in 20 days and B can do 34 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 34 of the same work in:

    A8 days
    B5 days
    C4 days
    D6 days
  • Question 3 - Select One

    A can do a work in 20 days and B can do the same work in 30 days in how many days canA and B together do the work?

    A15
    B16
    C10
    D12