Doubtnut Promotions Sticky

30 girls can finish a work in 40 days. After how many days should 10 girls leave the work so that it may be finished in 46 days, if all the 30 girls started the work?

A

18 days

B

28 days

C

22 days

D

30 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem, we need to determine after how many days 10 girls should leave the work so that the remaining work can be completed in a total of 46 days.

1. Calculate the Total Work:
The total work can be calculated in terms of "girl-days". If 30 girls can finish the work in 40 days, the total work is:
Total Work=30 girls×40 days=1200 girl-days

Hint: Remember that "girl-days" is a way to express the total amount of work done by a certain number of girls over a certain number of days.

2. Determine the Work Done in 46 Days:
Since we want the work to be completed in 46 days, we need to find out how much work can be done by 30 girls in the initial days and then by 20 girls after 10 girls leave.

3. Let x be the number of days all 30 girls work:
In the first x days, the work done by 30 girls is:
Work done=30 girls×x days=30x girl-days

4. Calculate Remaining Days:
After x days, the remaining days to complete the work will be:
Remaining Days=46x

5. Work Done by Remaining Girls:
After x days, 10 girls leave, so 20 girls will work for the remaining days. The work done by 20 girls in the remaining days is:
Work done=20 girls×(46x) days=20(46x) girl-days

6. Set Up the Equation:
The total work done by both phases must equal the total work:
30x+20(46x)=1200

7. Simplify the Equation:
Expanding the equation gives:
30x+92020x=1200
10x+920=1200

8. Solve for x:
Subtract 920 from both sides:
10x=280
Divide by 10:
x=28

9. Conclusion:
Therefore, the 10 girls should leave after 28 days.

Final Answer:
10 girls should leave the work after 28 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    30 workers can finish a work in 20 days. After how many days should 9 workers leave the job so that the work is completed in total 26 days if all the 30 workers started the work.

    A12
    B10
    C6
    Dnone of these
  • Question 2 - Select One

    30 workers can finish a work in 20 days. After how many days should 9 workers leave the job so that the work is completed in total 26 days :

    A12
    B10
    C6
    Dnone of these
  • Question 3 - Select One

    15 men can finish a piece of work in 40 days. The number of days after which 5 men should leave the work so that the work is finished in 45 days altogether is:

    A10
    B20
    C30
    D35