150 workers were engaged to finish a piece of work in a certain number of days. Four wirkers dropped from the work in the second day. Four workers dropped in third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed.Solution in Telugu
Step by step video & image solution for 150 workers were engaged to finish a piece of work in a certain number of days. Four wirkers dropped from the work in the second day. Four workers dropped in third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed. by Maths experts to help you in doubts & scoring excellent marks in Class 10 exams.
Topper's Solved these Questions
- BOOK - VGS PUBLICATION-BRILLIANTCHAPTER - PROGRESSIONSEXERCISE - Creative Bits for CCE Model Examination129videos
PROGRESSIONS
- BOOK - VGS PUBLICATION-BRILLIANTCHAPTER - PROBABILITY (MULTIPLE CHOICE QUESTION)EXERCISE - PROBABILITY (MULTIPLE CHOICE QUESTION)20videos
PROBABILITY (MULTIPLE CHOICE QUESTION)
- BOOK - VGS PUBLICATION-BRILLIANTCHAPTER - PROGRESSIONS (MULTIPLE CHOICE QUESTION)EXERCISE - PROGRESSIONS (MULTIPLE CHOICE QUESTION)20videos
PROGRESSIONS (MULTIPLE CHOICE QUESTION)
Similar Questions
How many terms of A.P. −6,−112,−5 …… are needed to obtain a sum -25?
07:28View SolutionThe probability that a leap year will have 52 tuesdays is………..
08:46View SolutionA circle with area A, is contained in the interior of a larger with area A1+A2. IF the radius of the larger circle is 3 units and A1,A2 and (A1+A2) are in A.P., then find the radius of smaller circle…..
02:36View Solution150 workers were engaged to finish a job in a certain number of days.4 workers dropped out on second day,4 more workers dropped out on the third day and so on.It took 8 more days to finish the work.Find the number of days in which the work was complete.
06:38View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.
02:01View SolutionAbout 150 workers were engaged to finish a piece of work in a certain number of days. Four workers stopped working on the second day, four more workers stopped their work on the third day and so on. It took 8 more days to finish the work. Then the number of days in which the work was completed is 29 days b. 24 days c. 25 days d. none of these
06:22View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four wirkers dropped from the work in the second day. Four workers dropped in third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed.
[ Let the no. of days to finish the work is 'x' then
150x=x+82[2×150+(x+8−1)(−4)]06:07View SolutionIf they are in G.P.Write next one terms.
a,2a, 3a, 4a,......08:23View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped from the work on the second day. Four workers dropped on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed. [Let the no.of days to finish the work is 'x' then
150x=x+82[2×150+(x+8−1)(−4)]08:23View Solution150 workers were engaged to finish a job in a certain number of days. 4 workers dropped out on second day, 4 more workers dropped out on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed.
10:57View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped from the work on the second day. Four workers dropped on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed. [Let the no.of days to finish the work is 'r' then
150x=x+82[2×150+(x+8−1)(−4)]04:58View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped from the work on the second day. Four workers dropped on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed. [Let the no.of days to finish the work is 'r' then
150x=x+82[2×150+(x+8−1)(−4)]05:27View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped from the work on the second day. Four workers dropped on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed. [Let the no.of days to finish the work is 'r' then
150x=x+82[2×150+(x+8−1)(−4)]04:01View Solution150 workers were engaged to finish a job in a certain number of days. 4 workers dropped out on second day, 4 more workers dropped out on third day and so on.
05:11View SolutionAbout 150 workers were engaged to finish a piece of work in a certain number of days. Four workers stopped working on the second day, four more workers stopped their work on the third day and so on. It took 8 more days to finish the work. Then the number of days in which the work was completed is 29 days b. 24 days c. 25 days d. none of these
06:02View SolutionIn a factory, 150 workers were engaged to finish a piece of work in a certain number of days. However, if 4 workers are dropped everyday, except the first day, it will take 8 more days to finish the work. Find the number of days in which the work was to be completed.
06:18View Solution