A company employed 200 workers to complete a certain work in 150 days. If only one-fourth of the work has been done in 50 days, then in order to complete the whole work in time, the number of additional workers to be employed was
300
200
100
600
Step by step video & image solution for A company employed 200 workers to complete a certain work in 150 days. If only one-fourth of the work has been done in 50 days, then in order to complete the whole work in time, the number of additional workers to be employed was by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Updated on:21/07/2023Topper's Solved these Questions
Similar Questions
20 workers working for 5 hours a day complete a work in 10 days . If 25 workers are employed to work 10 hours a day, what is the time required to complete the work ?
View SolutionA man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?
View Solution
Knowledge Check
If B can do three-fourth of a work in 3 days, then the time taken to complete the whole work is ____.
A6 daysB5 daysC4 daysD3 daysIf B can do three-fourth of a work in 3 days, then the time taken to complete the whole work is ____.
A6 daysB5 daysC4 daysD3 daysIf Rohit alone can complete one-fourth of a work in 32 days, then in how many days Rohit alone can complete the whole work?
A96 daysB128 daysC64 daysD118 days
A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?
View SolutionA group of workers promise to complete a piece of work in 10 days, but five of them do not report for work. If it took the remaining workers 12 days to complete the work, then the number of workers originally hired was 15 b. 25 c. 30 d. 45
View Solution20 workers working for 5 h per day complete a work in 10 days. If 25 workers are employed to work 10 h per day, what is the time required to complete the work?
View SolutionA can complete a piece of work in 25 days. After working for 5 days, remaining work is completed in 15 days with the help of B. Then B can complete the whole work in how many days?
View Solution56 workers canfinish a piece of work in 14 days. If the work
is to be completed in 8 days, then how many extra workers
are required ?
View Solution