A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?

A

75

B

85

C

100

D

120

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will use the information given and apply the concept of work done by men over time.

Step 1: Understand the Work Done
The man undertakes to complete a certain work in 150 days using 200 men. In 50 days, only a quarter (1/4) of the work is done.

Step 2: Calculate the Total Work
Since 1/4 of the work is completed in 50 days, the total work can be represented as:
- Total Work (W) = 4 * (Work done in 50 days)

Let’s denote the total work as W. If 1/4 of the work is done in 50 days, then:
- Work done in 50 days = W/4

Step 3: Calculate Work Done by 200 Men in 50 Days
The work done by 200 men in 50 days can be expressed as:
- Work done = Number of men × Number of days
- Work done = 200 men × 50 days = 10000 man-days

Step 4: Relate Work Done to Total Work
Since 1/4 of the total work is done in 50 days, we can set up the equation:
- W/4 = 10000 man-days
- Therefore, Total Work (W) = 10000 man-days × 4 = 40000 man-days

Step 5: Calculate Remaining Work
After 50 days, the remaining work is:
- Remaining Work = Total Work - Work done in 50 days
- Remaining Work = 40000 man-days - 10000 man-days = 30000 man-days

Step 6: Calculate Remaining Days
The total time to complete the work is 150 days. Since 50 days have already passed, the remaining days are:
- Remaining Days = 150 days - 50 days = 100 days

Step 7: Calculate Required Men to Complete Remaining Work
Let x be the number of additional men needed. The total number of men will then be (200 + x). The work that needs to be completed in the remaining days is 30000 man-days. We can set up the equation:
- (200 + x) men × 100 days = 30000 man-days

Step 8: Solve for x
Now, we can solve for x:
- 200 + x = 30000 man-days / 100 days
- 200 + x = 300
- x = 300 - 200
- x = 100

Conclusion
The number of additional men required to finish the work on time is 100.

|


Similar Questions


Knowledge Check

  • A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is:
    (A) 50 (B) 75 (C) 100 (D) 150

    A100
    B125
    C50
    D75
  • A contractor undertakes to make a mall in 60 days and he
    employs 30 men. After 30 days it is found that only one-
    third of the work is completed. How many extre men should
    he employ so that the work is completed on time?

    A20 men
    B25 men
    C30 men
    D40 men
  • A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only onethird of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?

    A100
    B60
    C75
    DNone of these