A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?
75
85
100
120
To solve the problem step by step, we will use the information given and apply the concept of work done by men over time.
Step 1: Understand the Work Done
The man undertakes to complete a certain work in 150 days using 200 men. In 50 days, only a quarter (1/4) of the work is done.
Step 2: Calculate the Total Work
Since 1/4 of the work is completed in 50 days, the total work can be represented as:
- Total Work (W) = 4 * (Work done in 50 days)
Let’s denote the total work as W. If 1/4 of the work is done in 50 days, then:
- Work done in 50 days = W/4
Step 3: Calculate Work Done by 200 Men in 50 Days
The work done by 200 men in 50 days can be expressed as:
- Work done = Number of men × Number of days
- Work done = 200 men × 50 days = 10000 man-days
Step 4: Relate Work Done to Total Work
Since 1/4 of the total work is done in 50 days, we can set up the equation:
- W/4 = 10000 man-days
- Therefore, Total Work (W) = 10000 man-days × 4 = 40000 man-days
Step 5: Calculate Remaining Work
After 50 days, the remaining work is:
- Remaining Work = Total Work - Work done in 50 days
- Remaining Work = 40000 man-days - 10000 man-days = 30000 man-days
Step 6: Calculate Remaining Days
The total time to complete the work is 150 days. Since 50 days have already passed, the remaining days are:
- Remaining Days = 150 days - 50 days = 100 days
Step 7: Calculate Required Men to Complete Remaining Work
Let x be the number of additional men needed. The total number of men will then be (200 + x). The work that needs to be completed in the remaining days is 30000 man-days. We can set up the equation:
- (200 + x) men × 100 days = 30000 man-days
Step 8: Solve for x
Now, we can solve for x:
- 200 + x = 30000 man-days / 100 days
- 200 + x = 300
- x = 300 - 200
- x = 100
Conclusion
The number of additional men required to finish the work on time is 100.
The man undertakes to complete a certain work in 150 days using 200 men. In 50 days, only a quarter (1/4) of the work is done.
Since 1/4 of the work is completed in 50 days, the total work can be represented as:
- Total Work (W) = 4 * (Work done in 50 days)
- Work done in 50 days = W/4
The work done by 200 men in 50 days can be expressed as:
- Work done = Number of men × Number of days
- Work done = 200 men × 50 days = 10000 man-days
Since 1/4 of the total work is done in 50 days, we can set up the equation:
- W/4 = 10000 man-days
- Therefore, Total Work (W) = 10000 man-days × 4 = 40000 man-days
After 50 days, the remaining work is:
- Remaining Work = Total Work - Work done in 50 days
- Remaining Work = 40000 man-days - 10000 man-days = 30000 man-days
The total time to complete the work is 150 days. Since 50 days have already passed, the remaining days are:
- Remaining Days = 150 days - 50 days = 100 days
Let x be the number of additional men needed. The total number of men will then be (200 + x). The work that needs to be completed in the remaining days is 30000 man-days. We can set up the equation:
- (200 + x) men × 100 days = 30000 man-days
Now, we can solve for x:
- 200 + x = 30000 man-days / 100 days
- 200 + x = 300
- x = 300 - 200
- x = 100
The number of additional men required to finish the work on time is 100.
Similar Questions
A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?
View SolutionA contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
View Solution
Knowledge Check
A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is:
(A) 50 (B) 75 (C) 100 (D) 150A100B125C50D75A contractor undertakes to make a mall in 60 days and he
employs 30 men. After 30 days it is found that only one-
third of the work is completed. How many extre men should
he employ so that the work is completed on time?A20 menB25 menC30 menD40 menA contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only onethird of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
A100B60C75DNone of these
A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that they had already done 23 of the work.
How many men can be discharged now so that the work may finish in time?
View SolutionA contractor undertakes to do a piece of work in 96 days. He engages 100 men at the begin ning. But in the 1/6 of the scheduled time, 1/7 of work is completed. How many additional men should be employed so that the work will be com pleted in time?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 23 of the work. How many men can be discharge now so that the work may finish in time?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work may finish in time ?
View SolutionA contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?
View Solution