A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?
C
D
A
B
Step by step video & image solution for A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Updated on:21/07/2023Similar Questions
A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?
View SolutionA contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only onethird of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
View Solution
Knowledge Check
A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is:
(A) 50 (B) 75 (C) 100 (D) 150A100B125C50D75A contractor undertakes to make a mall in 60 days and he
employs 30 men. After 30 days it is found that only one-
third of the work is completed. How many extre men should
he employ so that the work is completed on time?A20 menB25 menC30 menD40 menA contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
A70B75C80D85
A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that they had already done 23 of the work.
How many men can be discharged now so that the work may finish in time?
View SolutionA contractor undertakes to do a piece of work in 96 days. He engages 100 men at the begin ning. But in the 1/6 of the scheduled time, 1/7 of work is completed. How many additional men should be employed so that the work will be com pleted in time?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work may finish in time ?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 23 of the work. How many men can be discharge now so that the work may finish in time?
View SolutionA contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?
View Solution