150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped from the work on the second day. Four workers dropped on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed. [Let the no.of days to finish the work is 'r' then
150x=x+82[2×150+(x+81)(4)]
Solution in Tamil

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:25 days


Suppose the work is completed in n days. Since 4 workers dropped every day except the first day, the total amount of work done in n days is the sum of n terms of an A.P. with first term 150 and common difference -4.
Total amount of work done
=n2[2×150+(n1)×(4)]=n(1522n)
Had the workers not dropped, the work would have finished in (n-8) days with 150 workers working each day. Therefore, the total amount of work done in n days is 150 (n-8).
n(152-2n)=150(n-8)
n2n600=0
(n25)(n+24)=0
n=25
Thus, the work is completed in 25 days

Updated on:21/07/2023
|


Topper's Solved these Questions


Similar Questions