The ratio of the efficiencies of A, B and C to do a certain work is 7:3: 5. Working together, they can complete work in 21 days. A and C worked together for 15 days. The remaining work will be completed by B alone in:
A, B और C की कार्य क्षमता का अनुपात 7 : 3 : 5 है | एक साथ कार्य करते हुए, वे किसी कार्य को 21 दिनों में पूरा कर सकते हैं | A और C ने एक साथ 15 दिनों तक कार्य किया | शेष कार्य पूरा करने में B को अकेले कितने दिन लगेंगे ?
a) 54 days
b) 45 days
c) 60 days
d) 63 days
To solve the problem step by step, we will follow these calculations:
Step 1: Determine the Total Efficiency
The efficiencies of A, B, and C are given in the ratio 7:3:5.
- Let the efficiencies be:
- Efficiency of A = 7x
- Efficiency of B = 3x
- Efficiency of C = 5x
The total efficiency of A, B, and C together is:
Total Efficiency=7x+3x+5x=15x
Step 2: Calculate Total Work
They can complete the work together in 21 days.
Using the formula:
Total Work=Total Efficiency×Time
Substituting the values:
Total Work=15x×21=315x
Step 3: Work Done by A and C Together
A and C work together for 15 days. Their combined efficiency is:
Efficiency of A + C=7x+5x=12x
The work done by A and C in 15 days is:
Work Done=Efficiency×Time=12x×15=180x
Step 4: Calculate Remaining Work
Now, we find the remaining work:
Remaining Work=Total Work−Work Done by A and C
Substituting the values:
Remaining Work=315x−180x=135x
Step 5: Determine Time Taken by B to Complete Remaining Work
B's efficiency is 3x. We need to find out how long it will take B to complete the remaining work of 135x.
Using the formula:
Time=WorkEfficiency
Substituting the values:
Time=135x3x=45 days
Final Answer
The remaining work will be completed by B alone in 45 days.
---
The efficiencies of A, B, and C are given in the ratio 7:3:5.
- Efficiency of A = 7x
- Efficiency of B = 3x
- Efficiency of C = 5x
Total Efficiency=7x+3x+5x=15x
They can complete the work together in 21 days.
Total Work=Total Efficiency×Time
Substituting the values:
Total Work=15x×21=315x
A and C work together for 15 days. Their combined efficiency is:
Efficiency of A + C=7x+5x=12x
Work Done=Efficiency×Time=12x×15=180x
Now, we find the remaining work:
Remaining Work=Total Work−Work Done by A and C
Substituting the values:
Remaining Work=315x−180x=135x
B's efficiency is 3x. We need to find out how long it will take B to complete the remaining work of 135x.
Time=WorkEfficiency
Substituting the values:
Time=135x3x=45 days
The remaining work will be completed by B alone in 45 days.
Topper's Solved these Questions
Similar Questions
To do a certain work, the ratio of the efficiencies of A , B and C is 7 : 5 : 6. Working together, they can complete the same work in 35 days. B and C worked together for 21 days. The remaining work will be completed by A alone in :
एक निश्चित कार्य को करने के लिए,A, B और C की कार्य क्षमता का अनुपात 7 : 5: 6 है| एक साथ कार्य करते हुए, वे इसी कार्य को 35 दिनों में पूरा कर सकते हैं | B और C ने 21 दिनों तक कार्य किया | शेष कार्य पूरा करने में A को अकेले कितने दिन लगेंगे ?View SolutionThe ratio of efficiencies of A , B and C is 3 : 5 : 1. Working together, they can complete a piece of work in 5 days. A and B worked together for 3 days. The remaining will be completed by C alone in :
A, B और C की कार्य क्षमता का अनुपात 3 : 5 : 1 है | एक साथ कार्य करते हुए, वे किसी कार्य को 5 दिनों में पूरा कर सकते हैं |A और B ने एक साथ 3 दिनों तक कार्य किया | C को अकेले शेष कार्य करने में कितना समय (दिन) लगेगा ?View Solution
Knowledge Check
- Question 1 - Select One
The ratio of the efficiencies of A, B and C to do a certain work is 7:3:5. Working together, they can complete the work in 21 days. A and C worked together for 5 days. The remaining work will be completed by B alone in :
A54 daysB45 daysC60 daysD85 days - Question 2 - Select One
The efficiencies of A, B and C are in the ratio 5: 3: 8. Working together they can complete a work in 30 days. A and B worked together for 20 days. The remaining work will be completed by C alone in:
A30 daysB32 daysC36 daysD40 days - Question 3 - Select One
The efficiences of A , B and C are in ratio 5 : 3 : 8. Working together they can complete a work in 30 days. A and B worked together for 20 days. The remaining work will be completed by C alone in :
A, B और C की कार्य क्षमता 5 : 3 : 8 है| एक साथ कार्य करते हुए, वे किसी कार्य को 30 दिनों में कर सकते हैं | A और B ने 20 दिनों तक कार्य किया | शेष कार्य पूरा करने में C को अकेले कितने दिन लगेंगे?A40 daysB36 daysC30 daysD32 days
The efficiences of A , B and C are in ratio 5 : 3 : 8. Working together they can complete a work in 30 days. A and B worked together for 20 days. The remaining work will be completed by C alone in :
A, B और C की कार्य क्षमता 5 : 3 : 8 है| एक साथ कार्य करते हुए, वे किसी कार्य को 30 दिनों में कर सकते हैं | A और B ने 20 दिनों तक कार्य किया | शेष कार्य पूरा करने में C को अकेले कितने दिन लगेंगे?View SolutionThe ratio of the efficiencies of A, B and C is 7:5:4. Working together, they can finish work in 35 days. A and B work together for 28 days. The remaining work will be completed (in days) by C alone:
A, B और C की कार्य क्षमता का अनुपात 7 : 5 : 4 है | एक साथ कार्य करते हुए, वे किसी कार्य को 35 दिनों में समाप्त कर सकते हैं | A और B एक साथ 28 दिनों तक कार्य करते हैं | C शेष कार्य कितने दिनों में पूरा करेगा ?View SolutionThe ratio of efficiencies of A , B and C is 7 : 5 : 8. Working together, they can complete a piece of work in 42 days. B and C worked together for 21 days and the remaining was completed by A alone. The whole work was completed in :
A, B और C की कार्य क्षमता का अनुपात 7 : 5 : 8 है | एक साथ कार्य करते हुए, वे किसी कार्य को 42 दिनों में कर सकते हैं |B और C ने एक साथ 21 दिनों तक कार्य किया और शेष कार्य A ने पूरा किया | पूरा कार्य कितने दिनों में समाप्त हुआ ?View SolutionThe ratio of the efficiencies of A, B and C is 3: 5:1. Working together, they can complete a piece of work in 5 days. A and B work together for 3 days. The remaining work will be completed by C alone in?
View SolutionTo do a certain work the ratio of the efficincies of A, B and C is 7:5:6. Working together they can complete the same work in 35 days. B and C work together for 21 days. The remaining work will be completed by A alone in:
View Solution