Doubtnut Promotions Sticky

To do a certain work, the ratio of the efficiencies of A , B and C is 7 : 5 : 6. Working together, they can complete the same work in 35 days. B and C worked together for 21 days. The remaining work will be completed by A alone in :
एक निश्चित कार्य को करने के लिए,A, B और C की कार्य क्षमता का अनुपात 7 : 5: 6 है| एक साथ कार्य करते हुए, वे इसी कार्य को 35 दिनों में पूरा कर सकते हैं | B और C ने 21 दिनों तक कार्य किया | शेष कार्य पूरा करने में A को अकेले कितने दिन लगेंगे ?

A

60 days

B

57 days

C

54 days

D

50 days

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will follow these calculations:

Step 1: Determine the total work done
The efficiency ratio of A, B, and C is given as 7:5:6. This means:
- A's efficiency = 7 units
- B's efficiency = 5 units
- C's efficiency = 6 units

Total efficiency of A, B, and C together = 7 + 5 + 6 = 18 units.

Since they can complete the work in 35 days, the total work (W) can be calculated as:
W=Total Efficiency×Time=18×35=630 units

Step 2: Calculate the work done by B and C in 21 days
The combined efficiency of B and C is:
Efficiency of B and C=5+6=11 units

The work done by B and C in 21 days is:
Work done by B and C=Efficiency of B and C×Time=11×21=231 units

Step 3: Calculate the remaining work
Now, we can find the remaining work after B and C have worked for 21 days:
Remaining Work=Total WorkWork done by B and C=630231=399 units

Step 4: Calculate the time taken by A to complete the remaining work
A's efficiency is 7 units. The time (T) taken by A to complete the remaining work is given by:
T=Remaining WorkEfficiency of A=3997

Calculating this gives:
T=57 days

Final Answer
Thus, the remaining work will be completed by A alone in 57 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    To do a certain work the ratio of the efficincies of A, B and C is 7:5:6. Working together they can complete the same work in 35 days. B and C work together for 21 days. The remaining work will be completed by A alone in:

    A60 days
    B57 days
    C54 days
    D50 days
  • Question 2 - Select One

    The ratio of the efficiencies of A, B and C is 3: 5:1. Working together, they can complete a piece of work in 5 days. A and B work together for 3 days. The remaining work will be completed by C alone in?

    A18 days
    B24 days
    C21 days
    D15 days
  • Question 3 - Select One

    The efficiencies of A, B and C are in the ratio 5: 3: 8. Working together they can complete a work in 30 days. A and B worked together for 20 days. The remaining work will be completed by C alone in:

    A30 days
    B32 days
    C36 days
    D40 days