The ratio of efficiencies of A , B and C is 7 : 5 : 8. Working together, they can complete a piece of work in 42 days. B and C worked together for 21 days and the remaining was completed by A alone. The whole work was completed in :
A, B और C की कार्य क्षमता का अनुपात 7 : 5 : 8 है | एक साथ कार्य करते हुए, वे किसी कार्य को 42 दिनों में कर सकते हैं |B और C ने एक साथ 21 दिनों तक कार्य किया और शेष कार्य A ने पूरा किया | पूरा कार्य कितने दिनों में समाप्त हुआ ?

A

96

B

99

C

102

D

93

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, let's break it down:

Step 1: Understand the efficiencies of A, B, and C
The efficiencies of A, B, and C are given in the ratio 7:5:8. We can denote their efficiencies as:
- Efficiency of A = 7x
- Efficiency of B = 5x
- Efficiency of C = 8x

Step 2: Calculate the total efficiency when A, B, and C work together
The total efficiency when A, B, and C work together is:
Total Efficiency=7x+5x+8x=20x

Step 3: Calculate the total work done
We know that A, B, and C can complete the work together in 42 days. Therefore, the total work (W) can be calculated as:
W=Total Efficiency×Time=20x×42=840x

Step 4: Calculate the efficiency of B and C together
The combined efficiency of B and C is:
Efficiency of B and C=5x+8x=13x

Step 5: Calculate the work done by B and C in 21 days
If B and C work together for 21 days, the work done (W_BC) is:
WBC=Efficiency of B and C×Time=13x×21=273x

Step 6: Calculate the remaining work to be done by A
The remaining work (W_remaining) that A has to complete is:
Wremaining=WWBC=840x273x=567x

Step 7: Calculate the time taken by A to complete the remaining work
A's efficiency is 7x, so the time taken by A to complete the remaining work (T_A) is:
TA=WremainingEfficiency of A=567x7x=81 days

Step 8: Calculate the total time taken to complete the work
The total time taken to complete the work is the sum of the time taken by B and C and the time taken by A:
Total Time=21 days (by B and C)+81 days (by A)=102 days

Final Answer
The whole work was completed in 102 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • The ratio of the efficiencies of A, B and C is 7:5:8. Working together, they can complete a piece of work in 42 days. B and C worked together for 21 days and the remaining work was completed by A alone. The whole work was completed in:

    A96 days
    B99 days
    C102 days
    DNone of these
  • The ratio of the efficiencies of A, B and C is 3: 5:1. Working together, they can complete a piece of work in 5 days. A and B work together for 3 days. The remaining work will be completed by C alone in?

    A18 days
    B24 days
    C21 days
    D15 days
  • The efficiencies of A, B and C are in the ratio 5: 3: 8. Working together they can complete a work in 30 days. A and B worked together for 20 days. The remaining work will be completed by C alone in:

    A30 days
    B32 days
    C36 days
    D40 days