Doubtnut Promotions Sticky

X did a task for 24 days and left it incomplete. He could have finished the task all by himself in a total of 36 days. Y, who can finish the task alone in 18 days, will take how many more days to complete the task?
X ने 24 दिनों के लिए एक कार्य किया और उसे अधूरा छोड़ दिया। वह कुल 36 दिनों में अकेला सारा काम पूरा कर सकता था। Y, जो 18 दिनों में अकेले कार्य पूरा कर सकता है, उसे इस कार्य को पूरा करने में कितने और दिन लगेंगे?

A

9

B

6

C

12

D

8

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will follow the reasoning outlined in the video transcript.

Step 1: Determine the total work done by X
X can complete the entire task in 36 days. Therefore, the work done by X in one day is:
Work done by X in one day=136
This means that in 24 days, the total work done by X is:
Work done by X in 24 days=24×136=2436=23

Step 2: Calculate the remaining work
Since the total work is considered as 1 (the whole task), the remaining work after X has worked for 24 days is:
Remaining work=123=13

Step 3: Determine the work rate of Y
Y can complete the entire task in 18 days. Therefore, the work done by Y in one day is:
Work done by Y in one day=118

Step 4: Calculate the time taken by Y to complete the remaining work
To find out how many days Y will take to complete the remaining 13 of the work, we can set up the equation:
Time taken by Y=Remaining workWork done by Y in one day=13118=13×18=6 days

Final Answer
Y will take 6 more days to complete the task.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    X and Y together can finish a task in 12 days. If Y alone can finish the same task in 15 days, then how many days will X alone take to finish the task ?

    A45
    B50
    C60
    D30
  • Question 2 - Select One

    Keerthi and Malathi together can complete a task in 12 days, while Malathi can finish it in 30 days. In how many days can Keerthi alone complete the task?

    A40 days
    B10 days
    C20 days
    D30 days
  • Question 3 - Select One

    A and B together can complete a particular task in 8 days. If
    B alone can complete the same task in 10 days, how many
    days will A take to complete the task if he works alone ?

    A28
    B36
    C40
    D32