A, B and C can complete a piece of work in 36 days, 54 days and 108 days respectively. They started working together, but 9 days after the start of work, A quit working and B also stopped working 3 days before the work was completed. How many days did C work?
A, B और C, एक कार्य को क्रमशः 36 दिनों, 54 दिनों और 108 दिनों में पूरा
कर सकते हैं | उन्होंने एक साथ कार्य करना शुरू किया, लेकिन कार्य शुरू होने के 9 दिनों के बाद A ने कार्य करना
छोड़ दिया और कार्य पूरा होने के 3 दिन पहले B ने भी कार्य करना छोड़ दिया | C ने कितने दिन कार्य किया?
29
33
31
30
To solve the problem, we will follow these steps:
Step 1: Calculate the work done by A, B, and C in one day.
- A can complete the work in 36 days, so the work done by A in one day = 1/36 of the work.
- B can complete the work in 54 days, so the work done by B in one day = 1/54 of the work.
- C can complete the work in 108 days, so the work done by C in one day = 1/108 of the work.
Step 2: Find the total work done by A, B, and C together in one day.
To find the combined work done by A, B, and C in one day, we add their individual work rates:
Work done in one day=136+154+1108
Step 3: Calculate the least common multiple (LCM) of the denominators.
The LCM of 36, 54, and 108 is 108. We will convert each fraction to have a common denominator of 108:
136=3108,154=2108,1108=1108
Now, adding these together:
Total work done in one day=3+2+1108=6108=118
Step 4: Calculate the total work done in the first 9 days.
In the first 9 days, A, B, and C work together:
Work done in 9 days=9×118=918=12
Step 5: Determine the remaining work.
Since the total work is 1 (whole work), the remaining work after 9 days is:
Remaining work=1−12=12
Step 6: Calculate how long B and C work together to finish the remaining work.
After 9 days, A quits. B continues to work until 3 days before the work is completed. Let’s denote the total time taken to complete the work as X days. Therefore, B works for X−3 days.
In those X−9 days (after A quits), B and C work together for X−9 days. The work done by B and C together in one day is:
Work done by B and C in one day=154+1108
Calculating this gives:
154=2108,so2+1108=3108=136
Step 7: Set up the equation for the remaining work.
The remaining work is 12:
(X−9)×136=12
Step 8: Solve for X.
Multiplying both sides by 36:
X−9=18⇒X=27
Step 9: Calculate how many days C worked.
C worked for the entire duration of the work, which is X days. Therefore, C worked for:
C worked for 27 days.
Final Answer:
C worked for 27 days.
---
- B can complete the work in 54 days, so the work done by B in one day = 1/54 of the work.
- C can complete the work in 108 days, so the work done by C in one day = 1/108 of the work.
Topper's Solved these Questions
Similar Questions
A, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?
View SolutionA, B and C can complete a piece of work in 12, 24 and 36 days respectively. A and B will together complete the same work in how many days?
View Solution
Knowledge Check
A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?
Aa)20Bb)19Cc)30Dd)31A, B and C can complete a piece of work in 5, 20 and 60 days respectively. Working together, they can complete the same work in how many days ?
A, B और C किसी कार्य को क्रमशः 5, 20 और 60 दिनों में पूरा कर सकते हैं | एक साथ कार्य करते हुए, वे इस कार्य को कितने दिनों में पूरा करेंगे ?A314B334C514D534A, B and C can complete a piece of work in 4, 20 and 60 days respectively. Working together, they can complete the same work in how many days ?
A, B और C किसी कार्य को क्रमशः 4, 20 और 60 दिनों में पूरा कर सकते हैं | एक साथ कार्य करते हुए वे इस कार्य को कितने दिनों में समाप्त करेंगे ?A5319B3119C5119D3319
A, B and C can complete a piece of work in 10, 20 and 60 days respectively. Working together they can complete the same work in how many days?
View SolutionA, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed? 4 b. 15 c. 7 d. 8
View SolutionA, B and c can complete a piece of work in 10, 20 and 60 days respectively. Working together can complete the same work in how many days?
View Solution