A, B and C can complete a piece of work in 36 days, 54 days and 108 days respectively. They started working together, but 9 days after the start of work, A quit working and B also stopped working 3 days before the work was completed. How many days did C work?
A, B और C, एक कार्य को क्रमशः 36 दिनों, 54 दिनों और 108 दिनों में पूरा कर सकते हैं | उन्होंने एक साथ कार्य करना शुरू किया, लेकिन कार्य शुरू होने के 9 दिनों के बाद A ने कार्य करना छोड़ दिया और कार्य पूरा होने के 3 दिन पहले B ने भी कार्य करना छोड़ दिया | C ने कितने दिन कार्य किया?

A

29

B

33

C

31

D

30

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem, we will follow these steps:

Step 1: Calculate the work done by A, B, and C in one day.

- A can complete the work in 36 days, so the work done by A in one day = 1/36 of the work.
- B can complete the work in 54 days, so the work done by B in one day = 1/54 of the work.
- C can complete the work in 108 days, so the work done by C in one day = 1/108 of the work.

Step 2: Find the total work done by A, B, and C together in one day.

To find the combined work done by A, B, and C in one day, we add their individual work rates:

Work done in one day=136+154+1108

Step 3: Calculate the least common multiple (LCM) of the denominators.

The LCM of 36, 54, and 108 is 108. We will convert each fraction to have a common denominator of 108:

136=3108,154=2108,1108=1108

Now, adding these together:

Total work done in one day=3+2+1108=6108=118

Step 4: Calculate the total work done in the first 9 days.

In the first 9 days, A, B, and C work together:

Work done in 9 days=9×118=918=12

Step 5: Determine the remaining work.

Since the total work is 1 (whole work), the remaining work after 9 days is:

Remaining work=112=12

Step 6: Calculate how long B and C work together to finish the remaining work.

After 9 days, A quits. B continues to work until 3 days before the work is completed. Let’s denote the total time taken to complete the work as X days. Therefore, B works for X3 days.

In those X9 days (after A quits), B and C work together for X9 days. The work done by B and C together in one day is:

Work done by B and C in one day=154+1108

Calculating this gives:

154=2108,so2+1108=3108=136

Step 7: Set up the equation for the remaining work.

The remaining work is 12:

(X9)×136=12

Step 8: Solve for X.

Multiplying both sides by 36:

X9=18X=27

Step 9: Calculate how many days C worked.

C worked for the entire duration of the work, which is X days. Therefore, C worked for:

C worked for 27 days.

Final Answer:

C worked for 27 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?

    Aa)20
    Bb)19
    Cc)30
    Dd)31
  • A, B and C can complete a piece of work in 5, 20 and 60 days respectively. Working together, they can complete the same work in how many days ?
    A, B और C किसी कार्य को क्रमशः 5, 20 और 60 दिनों में पूरा कर सकते हैं | एक साथ कार्य करते हुए, वे इस कार्य को कितने दिनों में पूरा करेंगे ?

    A314
    B334
    C514
    D534
  • A, B and C can complete a piece of work in 4, 20 and 60 days respectively. Working together, they can complete the same work in how many days ?
    A, B और C किसी कार्य को क्रमशः 4, 20 और 60 दिनों में पूरा कर सकते हैं | एक साथ कार्य करते हुए वे इस कार्य को कितने दिनों में समाप्त करेंगे ?

    A5319
    B3119
    C5119
    D3319