Doubtnut Promotions Sticky

A alone can complete a piece of work in 30 days.He left after the completion of half of the work.If B alone can complete the entire work in 16 days, then how many days will B take to complete the remaining work?
A किसी कार्य को अकेले 30 दिनों में पूरा कर सकता है | उसने आधा कार्य करके छोड़ दिया | यदि B अकेले पूरे कार्य को 16 दिनों में सकता है, तो B को शेष कार्य को पूरा करने में कितने दिन लगेंगे?

A

9

B

12

C

6

D

8

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will first determine how much work A and B can do individually and then calculate how long it will take B to finish the remaining work after A has completed half of it.

1. Determine A's Work Rate:
- A can complete the entire work in 30 days.
- Therefore, A's work rate is 130 of the work per day.

2. Calculate Work Done by A:
- A completes half of the work before leaving.
- Half of the work is 12.

3. Time Taken by A to Complete Half Work:
- To find out how many days A takes to complete half the work, we can use the formula:
Time=Work÷Work Rate
- Thus, the time taken by A to complete half the work is:
Time=12130=12×30=15 days

4. Determine B's Work Rate:
- B can complete the entire work in 16 days.
- Therefore, B's work rate is 116 of the work per day.

5. Calculate Remaining Work:
- After A has completed half of the work, the remaining work is also 12.

6. Time Taken by B to Complete Remaining Work:
- To find out how long it will take B to complete the remaining half of the work, we again use the formula:
Time=Work÷Work Rate
- Thus, the time taken by B to complete the remaining work is:
Time=12116=12×16=8 days

Final Answer:
B will take 8 days to complete the remaining work.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?

    A4
    B15
    C154
    D16
  • Question 2 - Select One

    Sunny can complete a piece of work in 30 days He worked for 6 days and left. Bunny completed the remaining work in 16 days. In how many days can the entire work kbe completed if they worik together?

    A8
    B12
    C16
    D20
  • Question 3 - Select One

    A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?

    A60 days
    B36 days
    C45 days
    D24 days