A alone can complete a piece of work in 30 days.He left after the completion of half of the work.If B alone can complete the entire work in 16 days, then how many days will B take to complete the remaining work?
A किसी कार्य को अकेले 30 दिनों में पूरा कर सकता है | उसने आधा कार्य करके छोड़ दिया | यदि B अकेले पूरे कार्य को 16 दिनों में सकता है, तो B को शेष कार्य को पूरा करने में कितने दिन लगेंगे?
9
12
6
8
To solve the problem step by step, we will first determine how much work A and B can do individually and then calculate how long it will take B to finish the remaining work after A has completed half of it.
1. Determine A's Work Rate:
- A can complete the entire work in 30 days.
- Therefore, A's work rate is 130 of the work per day.
2. Calculate Work Done by A:
- A completes half of the work before leaving.
- Half of the work is 12.
3. Time Taken by A to Complete Half Work:
- To find out how many days A takes to complete half the work, we can use the formula:
Time=Work÷Work Rate
- Thus, the time taken by A to complete half the work is:
Time=12130=12×30=15 days
4. Determine B's Work Rate:
- B can complete the entire work in 16 days.
- Therefore, B's work rate is 116 of the work per day.
5. Calculate Remaining Work:
- After A has completed half of the work, the remaining work is also 12.
6. Time Taken by B to Complete Remaining Work:
- To find out how long it will take B to complete the remaining half of the work, we again use the formula:
Time=Work÷Work Rate
- Thus, the time taken by B to complete the remaining work is:
Time=12116=12×16=8 days
Final Answer:
B will take 8 days to complete the remaining work.
- A can complete the entire work in 30 days.
- Therefore, A's work rate is 130 of the work per day.
- A completes half of the work before leaving.
- Half of the work is 12.
- To find out how many days A takes to complete half the work, we can use the formula:
Time=Work÷Work Rate
- Thus, the time taken by A to complete half the work is:
Time=12130=12×30=15 days
- B can complete the entire work in 16 days.
- Therefore, B's work rate is 116 of the work per day.
- After A has completed half of the work, the remaining work is also 12.
- To find out how long it will take B to complete the remaining half of the work, we again use the formula:
Time=Work÷Work Rate
- Thus, the time taken by B to complete the remaining work is:
Time=12116=12×16=8 days
B will take 8 days to complete the remaining work.
Topper's Solved these Questions
Similar Questions
A and B together can complete a work in 21 days. If A takes 42 days to complete the work alone, how many days will B take to complete the same work alone?
A और B मिलकर किसी कार्य को 21 दिनों में पूरा कर सकते हैं | यदि A कार्य पूरा अकेले करने में 42 दिन लेता है, तो B को उसी कार्य को अकेले पूरा करने में कितने दिन लगेंगे?
View SolutionA can do a piece of work in 30 days. He completed 40% of the work and left it. B completed the remaining work in 21 days. In how many days will A and B complete 65% of the same work together?
A किसी कार्य को 30 दिनों में कर सकता है | उसने 40% कार्य पूरा कर उसे छोड़ दिया | B ने शेष कार्य 21 दिनों में पूरा किया | एक साथ मिलकर कार्य करते हुए, A और B उसी कार्य का 65% कितने दिनों में पूरा करेंगे?
View Solution
Knowledge Check
A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
A4B15C154D16Sunny can complete a piece of work in 30 days He worked for 6 days and left. Bunny completed the remaining work in 16 days. In how many days can the entire work kbe completed if they worik together?
A8B12C16D20A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
A60 daysB36 daysC45 daysD24 days
A alone can complete a piece of work in 96 days. B is three times efficient than A is . A worked alone for 24 days after which B joined him. In how many days will they complete the remaining work together?
A किसी कार्य को अकेले 96 दिनों में पूरा कर सकता है | B, A से तीन गुना कुशल है | A ने 24 दिनों तक अकेले कार्य किया जिसके बाद B उससे जुड़ गया | वे एक साथ मिलकर शेष कार्य को कितने दिनों में पूरा करेंगे?
View SolutionAditya can complete a piece of work in 24 days alone. Raman can complete the same work in 45 days alone. In how many days they can complete the same work together?
आदित्य किसी कार्य को अकेला 24 दिन में पूरा कर सकता है | रमन उसी कार्य को अकेला 45 दिन में पूरा कर सकता है| वे दोनों मिलकर कार्य को कितने दिन में पूरा कर सकते हैं?
View SolutionA can do a work in 30 days, B can do the same work in 48 days. After working alone for 20 days A left and B started working, how long will B take to complete the work?
A किसी कार्य को 30 दिनों में कर सकता है,B इसी कार्य को 48 दिनों में कर सकता है | 20 दिन तक अकेले कार्य करने के बाद A ने छोड़ दिया तथा B ने कार्य करना शुरू कर दिया |B को इस कार्य को पूरा करने में कितना समय लगेगा ?
View SolutionA can complete a certain work in 35 days and B can complete the same work in 15 days. They worked together for 7 days, then B left the work. In how many days will A alone complete 60% of the remaining work?
A किसी कार्य को 35 दिनों में पूरा कर सकता है और B उसी कार्य को 15 दिनों में पूरा कर सकता है। उन्होंने 7 दिनों तक एक साथ कार्य किया, फिर B ने कार्य छोड़ दिया। कितने दिनों में A शेष कार्य का 60% पूरा करेगा?
View SolutionA can do a work in 12 days while B can do same work in 18 days. How long(in days) will it take if they do the work together?
A किसी कार्य को 12 दिनों में कर सकता है जबकि B इसी कार्य को 18 दिनों में कर सकता है | यदि वे साथ कार्य करें तो इसे पूरा होने में कितने दिन लगेंगे ?
View Solution