A can do a piece of work in 30 days. He completed 40% of the work and left it. B completed the remaining work in 21 days. In how many days will A and B complete 65% of the same work together?
A किसी कार्य को 30 दिनों में कर सकता है | उसने 40% कार्य पूरा कर उसे छोड़ दिया | B ने शेष कार्य 21 दिनों में पूरा किया | एक साथ मिलकर कार्य करते हुए, A और B उसी कार्य का 65% कितने दिनों में पूरा करेंगे?
13
10
1012
1312
To solve the problem step by step, we will follow the reasoning laid out in the video transcript.
Step 1: Determine the total work done by A
A can complete the entire work in 30 days. Therefore, we can consider the total work as 30 units (assuming 1 unit of work is done in 1 day).
Step 2: Calculate the work completed by A
A completed 40% of the work before leaving.
- Work completed by A = 40% of 30
- Work completed by A = (40/100) * 30 = 12 units
Step 3: Calculate the remaining work
The remaining work after A has completed 40% is:
- Remaining work = Total work - Work completed by A
- Remaining work = 30 - 12 = 18 units
Step 4: Determine B's efficiency
B completed the remaining work (18 units) in 21 days.
Let B's efficiency be x units per day.
- Work done by B = Efficiency of B * Time taken by B
- 18 = x * 21
- Therefore, x = 18 / 21 = 6 / 7 units per day
Step 5: Calculate A's efficiency
A's efficiency can be calculated as:
- Efficiency of A = Total work / Total days = 30 / 30 = 1 unit per day
Step 6: Calculate combined efficiency of A and B
Now, we can find the combined efficiency of A and B:
- Combined efficiency = Efficiency of A + Efficiency of B
- Combined efficiency = 1 + (6/7) = 1 + 0.857 = 13/7 units per day
Step 7: Calculate the work to be done (65% of total work)
We need to find out how much work A and B need to complete together:
- Work to be done = 65% of total work
- Work to be done = (65/100) * 30 = 19.5 units
Step 8: Calculate the time taken to complete 65% of the work
Now, we can find the time taken by A and B to complete 19.5 units of work:
- Time taken = Work to be done / Combined efficiency
- Time taken = 19.5 / (13/7)
- Time taken = 19.5 * (7/13) = 19.5 * 0.5385 ≈ 10.5 days
Conclusion
Thus, A and B together will complete 65% of the work in approximately 10.5 days.
A can complete the entire work in 30 days. Therefore, we can consider the total work as 30 units (assuming 1 unit of work is done in 1 day).
A completed 40% of the work before leaving.
- Work completed by A = 40% of 30
- Work completed by A = (40/100) * 30 = 12 units
The remaining work after A has completed 40% is:
- Remaining work = Total work - Work completed by A
- Remaining work = 30 - 12 = 18 units
B completed the remaining work (18 units) in 21 days.
Let B's efficiency be x units per day.
- Work done by B = Efficiency of B * Time taken by B
- 18 = x * 21
- Therefore, x = 18 / 21 = 6 / 7 units per day
A's efficiency can be calculated as:
- Efficiency of A = Total work / Total days = 30 / 30 = 1 unit per day
Now, we can find the combined efficiency of A and B:
- Combined efficiency = Efficiency of A + Efficiency of B
- Combined efficiency = 1 + (6/7) = 1 + 0.857 = 13/7 units per day
We need to find out how much work A and B need to complete together:
- Work to be done = 65% of total work
- Work to be done = (65/100) * 30 = 19.5 units
Now, we can find the time taken by A and B to complete 19.5 units of work:
- Time taken = Work to be done / Combined efficiency
- Time taken = 19.5 / (13/7)
- Time taken = 19.5 * (7/13) = 19.5 * 0.5385 ≈ 10.5 days
Thus, A and B together will complete 65% of the work in approximately 10.5 days.
Topper's Solved these Questions
Similar Questions
A alone can complete a piece of work in 30 days.He left after the completion of half of the work.If B alone can complete the entire work in 16 days, then how many days will B take to complete the remaining work?
A किसी कार्य को अकेले 30 दिनों में पूरा कर सकता है | उसने आधा कार्य करके छोड़ दिया | यदि B अकेले पूरे कार्य को 16 दिनों में सकता है, तो B को शेष कार्य को पूरा करने में कितने दिन लगेंगे?
View SolutionA can complete a piece of work in 20 days and B can complete 20% of the work in 6 days. If they work together in how many days can they finish 50% of the work, if they work together ?
A किसी कार्य को 20 दिनों में तथा B इस कार्य के 20% भाग को 6 दिनों में पूरा कर सकता है | यदि वे साथ कार्य करें, तो वे इस कार्य का 50% भाग कितने दिनों में पूरा करेंगे ?
View SolutionAditya can complete a piece of work in 24 days alone. Raman can complete the same work in 45 days alone. In how many days they can complete the same work together?
आदित्य किसी कार्य को अकेला 24 दिन में पूरा कर सकता है | रमन उसी कार्य को अकेला 45 दिन में पूरा कर सकता है| वे दोनों मिलकर कार्य को कितने दिन में पूरा कर सकते हैं?
View SolutionA can do one-third of a work in 15 days, B can do 75% of the same work in 18 days and C can do the same work in 36 days. B and C work together for 8 days. In how many days will A alone complete the remaining work ?
A किसी कार्य का एक-तिहाई भाग 15 दिनों में पूरा कर सकता है |B इसी कार्य का 75% भाग 18 दिनों में तथा C यही कार्य 36 दिनों में कर सकता है | B और C 8 दिनों तक साथ कार्य करते हैं | A अकेला शेष कार्य कितने दिनों में पूरा करेगा ?
View SolutionA and B together can do a piece work in 20 days. B and C together can do the same work in 25 days. C and A together can do the same work in 15 days. In how many days A alone can do the work?
A तथा B मिलकर किसी कार्य को 20 दिन में कर सकते हैं | B तथा C मिलकर उसी कार्य को 25 दिन में कर सकते हैं | C तथा A मिलकर उसी कार्य को 15 दिन में कर सकते हैं | A अकेला उस कार्य को कितने दिनों में कर सकता है?
View SolutionA can complete some work in 35 days and B can complete the same work in 15 days. They worked together for 8 days, then B left the work. In how many days will A alone complete 60% of the remaining work?
A किसी कार्य को 35 दिनों में पूरा कर सकता है और B उसी कार्य को 15 दिनों में पूरा कर सकता है। उन्होंने 8 दिनों तक एक साथ कार्य किया, फिर B ने कार्य छोड़ दिया। कितने दिनों में A शेष कार्य का 60% पूरा करेगा?
View SolutionA can complete a certain work in 35 days and B can complete the same work in 15 days. They worked together for 7 days, then B left the work. In how many days will A alone complete 60% of the remaining work?
A किसी कार्य को 35 दिनों में पूरा कर सकता है और B उसी कार्य को 15 दिनों में पूरा कर सकता है। उन्होंने 7 दिनों तक एक साथ कार्य किया, फिर B ने कार्य छोड़ दिया। कितने दिनों में A शेष कार्य का 60% पूरा करेगा?
View SolutionA can do 40% of a work in 12 days, whereas B can do 60% of the same work in 15 days. Both work together for 10 days. C completes the remaining work alone in 4 days. A, B and C together will complete 28% of the same work in :
A किसी कार्य का 40% भाग 12 दिनों में कर सकता है जबकि B इसी कार्य का 60% भाग 15 दिनों में कर सकता है |दोनों 10 दिनों तक एक साथ कार्य करते हैं | C शेष कार्य 4 दिनों में पूरा करता है | A, B और C एक साथ इसी कार्य का 28% भाग कितने दिनों में पूरा करेंगे ?
View SolutionA can do 13 of work in 30 days, B can do 25 of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the work in:
A 30 दिनों में 13 कार्य कर सकता है, B, 24 दिनों में उसी कार्य के 25 भाग को कर सकता है। उन्होंने 20 दिनों तक साथ कार्य किया। C ने शेष कार्य 8 दिनों में पूरा किया। A, B और C के एक साथ कार्य करने से कार्य कितने दिनों में पूरा हो जाएगा.?
View SolutionA can complete a work in 20 days and B in 2212 days. They both work together for 6 days and the remaining work is completed by C in 26 days. In how many days the work will be completed, if all the three work together? /
किसी कार्य को A, 20 दिनों में पूरा कर सकता है और B उसे 2212 दिनों में पूरा कर सकता है | वे दोनों मिलकर 6 दिनों तक एक साथ कार्य करते हैं और शेष कार्य को C द्वारा 26 दिनों में पूरा किया गया है | तीनों एक साथ मिलकर उसी कार्य को कितने दिनों में पूरा करेंगे?
View Solution