A can finish a piece of work in a certain number of days. B takes 45% more number of days to finish the same work independently. They worked together for 58 days and then the remaining work was done by B alone in 29 days. In how many days could A have completed the work, had he worked alone?
A किसी कार्य को को समाप्त कर सकता है जबकि B को स्वतंत्र रूप से इसी कार्य को करने में 45% अधिक दिन लगते हैं। उन्होंने एक साथ 58 दिनों तक कार्य किया तथा शेष कार्य B ने अकेले 29 दिनों में पूरा किया। A इस कार्य को अकेले कितने दिनों में समाप्त कर सकता था?
110 days/ दिन
118 days/ दिन
98 days/ दिन
120 days/ दिन
To solve the problem step by step, we will follow the reasoning outlined in the video transcript.
1. Assume the Time Taken by A:
Let the number of days taken by A to complete the work be 100 days.
Hint: Start by assuming a value for A's time to simplify calculations.
2. Calculate the Time Taken by B:
Since B takes 45% more time than A, we calculate B's time as follows:
Time taken by B=100+0.45×100=145 days
Hint: Use the percentage increase formula to find B's time.
3. Determine the Efficiency of A and B:
The efficiency of A and B can be expressed as the inverse of the time taken:
- Efficiency of A = 1100 work/day
- Efficiency of B = 1145 work/day
To find a common measure, we can express their efficiencies in terms of a common unit:
Efficiency of A=29 units/day(for calculation purposes)
Efficiency of B=20 units/day(for calculation purposes)
Hint: Remember that efficiency is the reciprocal of time.
4. Calculate Total Work Done Together in 58 Days:
When A and B work together for 58 days, the total work done is:
Total work done=(29+20)×58=49×58=2842 units
Hint: Combine their efficiencies to find the total work done together.
5. Calculate Remaining Work Done by B Alone in 29 Days:
The work done by B alone in 29 days is:
Remaining work=20×29=580 units
Hint: Use B's efficiency to find out how much work he completed alone.
6. Calculate Total Work:
The total work is the sum of the work done together and the work done by B alone:
Total work=2842+580=3422 units
Hint: Add the work done together and the work done alone to find the total.
7. Calculate the Time Taken by A to Complete the Total Work Alone:
The time taken by A to complete the total work is:
Time=Total workEfficiency of A=342229≈118 days
Hint: Divide the total work by A's efficiency to find the time.
Final Answer:
A could have completed the work alone in 118 days.
Let the number of days taken by A to complete the work be 100 days.
Since B takes 45% more time than A, we calculate B's time as follows:
Time taken by B=100+0.45×100=145 days
The efficiency of A and B can be expressed as the inverse of the time taken:
- Efficiency of A = 1100 work/day
- Efficiency of B = 1145 work/day
Efficiency of A=29 units/day(for calculation purposes)
Efficiency of B=20 units/day(for calculation purposes)
When A and B work together for 58 days, the total work done is:
Total work done=(29+20)×58=49×58=2842 units
The work done by B alone in 29 days is:
Remaining work=20×29=580 units
The total work is the sum of the work done together and the work done by B alone:
Total work=2842+580=3422 units
The time taken by A to complete the total work is:
Time=Total workEfficiency of A=342229≈118 days
A could have completed the work alone in 118 days.
Topper's Solved these Questions
Similar Questions
Two workers A and B together could finish a work in 8 days. They worked togetherfor 6 days and A left the work. The remaining work was completed by B alone in6 days. How many days would each take to complete the work individually ?
View SolutionP and Q can finish a work in 30 days. They worked at it for 10 days and then Q left. The remaining work is done byPalone in 20 more days. How long willPtake to finish the work alone?
View Solution
Knowledge Check
A and B can together finish a work in 30 days. They worked for it for 20 days and then B left. The remaining work was done by A alone in 20 more days. A alone can finish the work in…
A48 daysB50 daysC54 daysD60 daysIf A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many day can A alone complete the work?
A60 daysB45 daysC40 daysD30 daysA can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
A38B51C46D62
A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?
View SolutionX and Y can do a piece of work in 30 days. They work together for 6 days and thenX quits and Y finishes the work in 32 days . In how many days can Y do the piece of work alone ?
View SolutionA and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
View SolutionA can do a piece of work in 30 days. He worked for 6 days and B finished the remaining work in 48 days. B alone can do the whole work in how many days?
View SolutionA can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone?
View Solution