A can finish a piece of work in a certain number of days. B takes 45% more number of days to finish the same work independently. They worked together for 58 days and then the remaining work was done by B alone in 29 days. In how many days could A have completed the work, had he worked alone?
A किसी कार्य को को समाप्त कर सकता है जबकि B को स्वतंत्र रूप से इसी कार्य को करने में 45% अधिक दिन लगते हैं। उन्होंने एक साथ 58 दिनों तक कार्य किया तथा शेष कार्य B ने अकेले 29 दिनों में पूरा किया। A इस कार्य को अकेले कितने दिनों में समाप्त कर सकता था?

A

110 days/ दिन

B

118 days/ दिन

C

98 days/ दिन

D

120 days/ दिन

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will follow the reasoning outlined in the video transcript.

1. Assume the Time Taken by A:
Let the number of days taken by A to complete the work be 100 days.

Hint: Start by assuming a value for A's time to simplify calculations.

2. Calculate the Time Taken by B:
Since B takes 45% more time than A, we calculate B's time as follows:
Time taken by B=100+0.45×100=145 days

Hint: Use the percentage increase formula to find B's time.

3. Determine the Efficiency of A and B:
The efficiency of A and B can be expressed as the inverse of the time taken:
- Efficiency of A = 1100 work/day
- Efficiency of B = 1145 work/day

To find a common measure, we can express their efficiencies in terms of a common unit:
Efficiency of A=29 units/day(for calculation purposes)
Efficiency of B=20 units/day(for calculation purposes)

Hint: Remember that efficiency is the reciprocal of time.

4. Calculate Total Work Done Together in 58 Days:
When A and B work together for 58 days, the total work done is:
Total work done=(29+20)×58=49×58=2842 units

Hint: Combine their efficiencies to find the total work done together.

5. Calculate Remaining Work Done by B Alone in 29 Days:
The work done by B alone in 29 days is:
Remaining work=20×29=580 units

Hint: Use B's efficiency to find out how much work he completed alone.

6. Calculate Total Work:
The total work is the sum of the work done together and the work done by B alone:
Total work=2842+580=3422 units

Hint: Add the work done together and the work done alone to find the total.

7. Calculate the Time Taken by A to Complete the Total Work Alone:
The time taken by A to complete the total work is:
Time=Total workEfficiency of A=342229118 days

Hint: Divide the total work by A's efficiency to find the time.

Final Answer:
A could have completed the work alone in 118 days.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B can together finish a work in 30 days. They worked for it for 20 days and then B left. The remaining work was done by A alone in 20 more days. A alone can finish the work in…

    A48 days
    B50 days
    C54 days
    D60 days
  • If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many day can A alone complete the work?

    A60 days
    B45 days
    C40 days
    D30 days
  • A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?

    A38
    B51
    C46
    D62