A can do a work in 21 days and B in 42 days. If they work on it together for 7 days, then what fraction of work is left?
13
14
23
12
The correct Answer is:D
To solve the problem step by step, we will follow these instructions:
Step 1: Determine the work done by A and B
- A can complete the work in 21 days.
- B can complete the work in 42 days.
Step 2: Calculate the rate of work for A and B
- The rate of work is calculated using the formula:
Rate=WorkTime
- We can assume the total work to be the least common multiple (LCM) of 21 and 42, which is 42.
For A:
- Work = 42
- Time = 21
- Rate of A = 4221=2
For B:
- Work = 42
- Time = 42
- Rate of B = 4242=1
Step 3: Calculate the combined rate of A and B
- When A and B work together, their rates add up:
Combined Rate=Rate of A+Rate of B=2+1=3
Step 4: Calculate the work done when A and B work together for 7 days
- Work done in 7 days = Combined Rate × Time
Work done=3×7=21
Step 5: Determine the total work
- The total work is assumed to be 42 (as calculated from the LCM).
Step 6: Calculate the work remaining
- Work remaining = Total Work - Work Done
Work remaining=42−21=21
Step 7: Calculate the fraction of work left
- Fraction of work left = Work remainingTotal Work
Fraction of work left=2142=12
Final Answer:
The fraction of work left is 12.
---
- A can complete the work in 21 days.
- B can complete the work in 42 days.
- The rate of work is calculated using the formula:
Rate=WorkTime
- We can assume the total work to be the least common multiple (LCM) of 21 and 42, which is 42.
- Work = 42
- Time = 21
- Rate of A = 4221=2
- Work = 42
- Time = 42
- Rate of B = 4242=1
- When A and B work together, their rates add up:
Combined Rate=Rate of A+Rate of B=2+1=3
- Work done in 7 days = Combined Rate × Time
Work done=3×7=21
- The total work is assumed to be 42 (as calculated from the LCM).
- Work remaining = Total Work - Work Done
Work remaining=42−21=21
- Fraction of work left = Work remainingTotal Work
Fraction of work left=2142=12
The fraction of work left is 12.
Topper's Solved these Questions
Similar Questions
A can do a work in 15 days and B in 20 days.If they together work on it for 4 days, then the fraction of the work that is left is:
View SolutionA can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is 14 b. 110 c. 71 d. 815
View Solution
Knowledge Check
- Question 1 - Select One
A can do a work in 36 days and B in 12 days. If they work on it together for 3 days, then what fraction of work is left?
A23B13C14D15 - Question 2 - Select One
A can do a work in 72 days and B in 90 days. If they work on it together for 10 days, then what fraction of work is left?
A34B14C45D56 - Question 3 - Select One
A can do a work in 72 days and B in 90 days. If they work on it together for 10 days, then what fraction of work is left ?
A34B14C45D56
A can do a work in 20 days and B can do it in 14 days. If they work together for 7 days, then the fraction of the work left is:
View SolutionA alone can do a task in 35 days and B alone in 14 days. If they work on it together for 4 days, then what fraction of the task is left?
View SolutionA can do a work in 15 days and B in 20 days. If they together work on it for 4 days, then the fraction of the work that is left is :
View SolutionA can do a work in 15 days and B in 20 days.If they together work on it for 4 days, then the fraction of the work that is left is:
View SolutionA can do a piece of work in 15 days and B in 20 days. If they together work on it for 4 days, then the fraction of the work that is left is :
View Solution