P and Q together can do a job in 6 days. Q and R can finish the same job in 607 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is.
12
10
15
8
The correct Answer is:B
To solve the problem, we will break it down step by step.
Step 1: Determine the work rates of P, Q, and R.
Given:
- P and Q together can complete the job in 6 days.
- Q and R can complete the job in 607 days.
Work rate of P and Q:
If P and Q can complete the job in 6 days, their combined work rate is:
Work rate of P and Q=16 (jobs per day)
Work rate of Q and R:
If Q and R can complete the job in 607 days, their combined work rate is:
Work rate of Q and R=760 (jobs per day)
Step 2: Set up equations for individual work rates.
Let:
- Work rate of P = p
- Work rate of Q = q
- Work rate of R = r
From the above information, we have:
1. p+q=16 (1)
2. q+r=760 (2)
Step 3: Solve the equations.
From equation (1):
q=16−p
Substituting q in equation (2):
(16−p)+r=760
r=760−16+p
Convert 16 to a fraction with a denominator of 60:
16=1060
Thus,
r=760−1060+p=p−360=p−120
Step 4: Find the total work done.
Now, we need to find how much work is done when P works for 3 days and then Q and R work for 6 days.
Work done by P in 3 days:
Work by P=3p
Work done by Q and R in 6 days:
Work by Q and R=6(q+r)=6⋅760=4260=710
Step 5: Calculate total work done.
Total work done:
Total work=3p+710
Step 6: Find the remaining work.
The total work is 1 (the whole job), so:
1=3p+710
3p=1−710=310
p=110
Step 7: Find Q's and R's work rates.
Using p:
q=16−p=16−110
Finding a common denominator (30):
q=530−330=230=115
Now substituting q back to find r:
r=760−q=760−115=760−460=360=120
Step 8: Calculate the time taken by P and R to complete the job.
Time taken by P:
Time by P=1p=1110=10 days
Time taken by R:
Time by R=1r=1120=20 days
Step 9: Find the difference in days.
The difference in days between R and P:
Difference=20−10=10 days
Final Answer:
The difference in days in which R and P can complete the job is 10 days.
---
- P and Q together can complete the job in 6 days.
- Q and R can complete the job in 607 days.
If P and Q can complete the job in 6 days, their combined work rate is:
Work rate of P and Q=16 (jobs per day)
If Q and R can complete the job in 607 days, their combined work rate is:
Work rate of Q and R=760 (jobs per day)
- Work rate of P = p
- Work rate of Q = q
- Work rate of R = r
1. p+q=16 (1)
2. q+r=760 (2)
q=16−p
(16−p)+r=760
r=760−16+p
16=1060
Thus,
r=760−1060+p=p−360=p−120
Work by P=3p
Work by Q and R=6(q+r)=6⋅760=4260=710
Total work=3p+710
1=3p+710
3p=1−710=310
p=110
q=16−p=16−110
Finding a common denominator (30):
q=530−330=230=115
r=760−q=760−115=760−460=360=120
Time by P=1p=1110=10 days
Time by R=1r=1120=20 days
Difference=20−10=10 days
The difference in days in which R and P can complete the job is 10 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
P and Q together can do a job in 6 days. Q and R can finish the same job in 607 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is.
A15B10C8D12 - Question 2 - Select One
A and B together can finish a job in 24 days, while A, B and C together can finish the same job in 8 days. C alone will finish the job in
A12 daysB14 daysC16 daysD24 days - Question 3 - Select One
A,B and C together can finish a job in 4 days .A and B together can finish the same job in 5 days .In how many days ,C alone will finish the same job ?
A12B16C20D24
A can do a job in 12 days and B can do the same job in 6 days, in how many days working together they can complete the job?
View SolutionP and Q can do a job in 2 days, Q and R can do it in 4 days, and P and R in 12/5 days. What is the number of days required for P alone to do the job?
View SolutionP and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?
View SolutionA can do a job in 16 days and B can do the same job in 12 days. With the help of C, they can finish the job in 6 days only. Then, C alone can finish it in
View SolutionP can make a table in 16 days while Q can make it in 20 days. Q started the work and did that work for 5 days. In how many days P can complete the remaining work?
View Solution