Doubtnut Promotions Sticky

P and Q together can do a job in 6 days. Q and R can finish the same job in 607 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is.

A

12

B

10

C

15

D

8

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem, we will break it down step by step.

Step 1: Determine the work rates of P, Q, and R.

Given:
- P and Q together can complete the job in 6 days.
- Q and R can complete the job in 607 days.

Work rate of P and Q:
If P and Q can complete the job in 6 days, their combined work rate is:
Work rate of P and Q=16 (jobs per day)

Work rate of Q and R:
If Q and R can complete the job in 607 days, their combined work rate is:
Work rate of Q and R=760 (jobs per day)

Step 2: Set up equations for individual work rates.

Let:
- Work rate of P = p
- Work rate of Q = q
- Work rate of R = r

From the above information, we have:
1. p+q=16 (1)
2. q+r=760 (2)

Step 3: Solve the equations.

From equation (1):
q=16p

Substituting q in equation (2):
(16p)+r=760
r=76016+p

Convert 16 to a fraction with a denominator of 60:
16=1060
Thus,
r=7601060+p=p360=p120

Step 4: Find the total work done.

Now, we need to find how much work is done when P works for 3 days and then Q and R work for 6 days.

Work done by P in 3 days:
Work by P=3p

Work done by Q and R in 6 days:
Work by Q and R=6(q+r)=6760=4260=710

Step 5: Calculate total work done.

Total work done:
Total work=3p+710

Step 6: Find the remaining work.

The total work is 1 (the whole job), so:
1=3p+710
3p=1710=310
p=110

Step 7: Find Q's and R's work rates.

Using p:
q=16p=16110
Finding a common denominator (30):
q=530330=230=115

Now substituting q back to find r:
r=760q=760115=760460=360=120

Step 8: Calculate the time taken by P and R to complete the job.

Time taken by P:
Time by P=1p=1110=10 days

Time taken by R:
Time by R=1r=1120=20 days

Step 9: Find the difference in days.

The difference in days between R and P:
Difference=2010=10 days

Final Answer:
The difference in days in which R and P can complete the job is 10 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    P and Q together can do a job in 6 days. Q and R can finish the same job in 607 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is.

    A15
    B10
    C8
    D12
  • Question 2 - Select One

    A and B together can finish a job in 24 days, while A, B and C together can finish the same job in 8 days. C alone will finish the job in

    A12 days
    B14 days
    C16 days
    D24 days
  • Question 3 - Select One

    A,B and C together can finish a job in 4 days .A and B together can finish the same job in 5 days .In how many days ,C alone will finish the same job ?

    A12
    B16
    C20
    D24