Doubtnut Promotions Sticky

A can do a piece of work in 10 days and B can do it in 12 days. They work together for 3 days. Then B leaves and A alone continues. 2 days after that C joins and the work is completed in 2 days more. In how many days can C do it, if he works alone ?

A

40 days

B

50 days

C

40 days

D

60 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will follow these calculations:

Step 1: Determine the work efficiencies of A and B
- A can complete the work in 10 days, so A's efficiency is:
Efficiency of A=1 work10 days=110 work/day
- B can complete the work in 12 days, so B's efficiency is:
Efficiency of B=1 work12 days=112 work/day

Step 2: Calculate the combined efficiency of A and B
- The combined efficiency of A and B is:
Combined Efficiency=110+112
- To add these fractions, find a common denominator (which is 60):
Combined Efficiency=660+560=1160 work/day

Step 3: Calculate the work done by A and B in 3 days
- The amount of work done by A and B together in 3 days is:
Work done in 3 days=3×1160=3360=1120 of the work

Step 4: Determine the remaining work
- The total work is 1 (or 60 units if we consider the total work as 60 units). Thus, the remaining work after 3 days is:
Remaining Work=11120=920 of the work

Step 5: Calculate the work done by A alone in the next 2 days
- A continues to work alone for 2 days. The work done by A in 2 days is:
Work done by A in 2 days=2×110=210=15 of the work

Step 6: Determine the remaining work after A's 2 days
- The remaining work after A works for 2 days is:
Remaining Work=92015=920420=520=14 of the work

Step 7: Calculate the time taken by A and C together to finish the remaining work
- A's efficiency is 110 and let C's efficiency be c. Together, their efficiency is:
Efficiency of A and C=110+c
- They complete the remaining 14 of the work in 2 days:
2(110+c)=14
Simplifying gives:
110+c=18
c=18110
Finding a common denominator (40):
c=540440=140 work/day

Step 8: Calculate the number of days C would take to complete the work alone
- If C's efficiency is 140, then the time taken by C to complete the entire work alone is:
Time taken by C=1 work140 work/day=40 days

Thus, C can complete the work alone in 40 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a piece of work in 120 days and B can do it in 150 days. They work together for 20 days. Then B leaves and A alone continues the work. 12 days after that C joins A and the work is completed in 48 days more. In how many days can C do it if he works alone?

    A230 days
    B225 days
    C240 days
    D220 days
  • Question 2 - Select One

    A can do a work in 20 days. A and B can do it in 12 days together. In how many days B can do it alone?

    A25
    B20
    C30
    D15
  • Question 3 - Select One

    A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. In how many days, A alone can finish the remaining work?

    A7days
    B712 days
    C8 days
    D812days