A can do a piece of work in 10 days and B can do it in 12 days. They work together for 3 days. Then B leaves and A alone continues. 2 days after that C joins and the work is completed in 2 days more. In how many days can C do it, if he works alone ?
40 days
50 days
40 days
60 days
The correct Answer is:C
To solve the problem step by step, we will follow these calculations:
Step 1: Determine the work efficiencies of A and B
- A can complete the work in 10 days, so A's efficiency is:
Efficiency of A=1 work10 days=110 work/day
- B can complete the work in 12 days, so B's efficiency is:
Efficiency of B=1 work12 days=112 work/day
Step 2: Calculate the combined efficiency of A and B
- The combined efficiency of A and B is:
Combined Efficiency=110+112
- To add these fractions, find a common denominator (which is 60):
Combined Efficiency=660+560=1160 work/day
Step 3: Calculate the work done by A and B in 3 days
- The amount of work done by A and B together in 3 days is:
Work done in 3 days=3×1160=3360=1120 of the work
Step 4: Determine the remaining work
- The total work is 1 (or 60 units if we consider the total work as 60 units). Thus, the remaining work after 3 days is:
Remaining Work=1−1120=920 of the work
Step 5: Calculate the work done by A alone in the next 2 days
- A continues to work alone for 2 days. The work done by A in 2 days is:
Work done by A in 2 days=2×110=210=15 of the work
Step 6: Determine the remaining work after A's 2 days
- The remaining work after A works for 2 days is:
Remaining Work=920−15=920−420=520=14 of the work
Step 7: Calculate the time taken by A and C together to finish the remaining work
- A's efficiency is 110 and let C's efficiency be c. Together, their efficiency is:
Efficiency of A and C=110+c
- They complete the remaining 14 of the work in 2 days:
2(110+c)=14
Simplifying gives:
110+c=18
c=18−110
Finding a common denominator (40):
c=540−440=140 work/day
Step 8: Calculate the number of days C would take to complete the work alone
- If C's efficiency is 140, then the time taken by C to complete the entire work alone is:
Time taken by C=1 work140 work/day=40 days
Thus, C can complete the work alone in 40 days.
---
- A can complete the work in 10 days, so A's efficiency is:
Efficiency of A=1 work10 days=110 work/day
- B can complete the work in 12 days, so B's efficiency is:
Efficiency of B=1 work12 days=112 work/day
- The combined efficiency of A and B is:
Combined Efficiency=110+112
- To add these fractions, find a common denominator (which is 60):
Combined Efficiency=660+560=1160 work/day
- The amount of work done by A and B together in 3 days is:
Work done in 3 days=3×1160=3360=1120 of the work
- The total work is 1 (or 60 units if we consider the total work as 60 units). Thus, the remaining work after 3 days is:
Remaining Work=1−1120=920 of the work
- A continues to work alone for 2 days. The work done by A in 2 days is:
Work done by A in 2 days=2×110=210=15 of the work
- The remaining work after A works for 2 days is:
Remaining Work=920−15=920−420=520=14 of the work
- A's efficiency is 110 and let C's efficiency be c. Together, their efficiency is:
Efficiency of A and C=110+c
- They complete the remaining 14 of the work in 2 days:
2(110+c)=14
Simplifying gives:
110+c=18
c=18−110
Finding a common denominator (40):
c=540−440=140 work/day
- If C's efficiency is 140, then the time taken by C to complete the entire work alone is:
Time taken by C=1 work140 work/day=40 days
Topper's Solved these Questions
Similar Questions
A can do a piece of work in 120 days and B can do it in 150 days. The work together for 20 days. Then, B leave and A alone continues the work. 12 days after that C joins A and the work is completed in 48 days more. In how many days can C do it, if he works alone?
View SolutionA can do a piece of work in 6 days and A alone can do it in 10 days.In how many days can B alone do it?.
View Solution
Knowledge Check
- Question 1 - Select One
A can do a piece of work in 120 days and B can do it in 150 days. They work together for 20 days. Then B leaves and A alone continues the work. 12 days after that C joins A and the work is completed in 48 days more. In how many days can C do it if he works alone?
A230 daysB225 daysC240 daysD220 days - Question 2 - Select One
A can do a work in 20 days. A and B can do it in 12 days together. In how many days B can do it alone?
A25B20C30D15 - Question 3 - Select One
A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. In how many days, A alone can finish the remaining work?
A7daysB712 daysC8 daysD812days
A can do a piece of work in 20 days and B in 15 days. With help of C, they finish the work in 5 days. C can alone do the work in
View SolutionA can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together?
View SolutionA alone can do a piece of work in 10 days and B alone can do it in 15 days. In how many days will A and B together do the same work?
View SolutionA and B together can do a piece of work in 8 days. B alone can do it in 12 days. B alone works at it for 4 days. In how many more days after that could A alone complete it.
View SolutionA and B together do a piece of work in 15 days. B can do it alone in 20 days. In how many days can A do it alone.
View Solution