A contractor undertakes to do a piece of work in 96 days. He engages 100 men at the begin ning. But in the 1/6 of the scheduled time, 1/7 of work is completed. How many additional men should be employed so that the work will be com pleted in time?
30
20
15
10
The correct Answer is:B
To solve the problem step by step, we can follow these calculations:
Step 1: Determine the total work and the time taken
The contractor has undertaken to complete the work in 96 days. We denote the total work as W.
Step 2: Calculate the time elapsed and work completed
In 16 of the scheduled time:
Time elapsed=966=16 days
In this time, 17 of the work is completed:
Work completed=W7
Step 3: Calculate the remaining work
The remaining work after 16 days is:
Remaining work=W−W7=7W7−W7=6W7
Step 4: Determine the remaining time
The total time for the project is 96 days, and 16 days have already been used. Thus, the remaining time is:
Remaining time=96−16=80 days
Step 5: Set up the equation for the remaining work
Let x be the additional number of men needed. The total number of men working now is 100+x. The work rate for 100+x men over the remaining 80 days must equal the remaining work:
(100+x)×Rate×80=6W7
Step 6: Calculate the rate of work
The rate of work done by 100 men in 16 days is:
100×Rate×16=W7
From this, we can express the rate:
Rate=W7×100×16=W11200
Step 7: Substitute the rate into the remaining work equation
Substituting the rate back into the equation:
(100+x)×W11200×80=6W7
Step 8: Simplify the equation
Cancelling W from both sides:
(100+x)×8011200=67
(100+x)×1140=67
Multiplying both sides by 140:
100+x=6×1407
100+x=120
Step 9: Solve for x
x=120−100=20
Final Answer
The contractor needs to employ 20 additional men to complete the work on time.
---
The contractor has undertaken to complete the work in 96 days. We denote the total work as W.
In 16 of the scheduled time:
Time elapsed=966=16 days
In this time, 17 of the work is completed:
Work completed=W7
The remaining work after 16 days is:
Remaining work=W−W7=7W7−W7=6W7
The total time for the project is 96 days, and 16 days have already been used. Thus, the remaining time is:
Remaining time=96−16=80 days
Let x be the additional number of men needed. The total number of men working now is 100+x. The work rate for 100+x men over the remaining 80 days must equal the remaining work:
(100+x)×Rate×80=6W7
The rate of work done by 100 men in 16 days is:
100×Rate×16=W7
From this, we can express the rate:
Rate=W7×100×16=W11200
Substituting the rate back into the equation:
(100+x)×W11200×80=6W7
Cancelling W from both sides:
(100+x)×8011200=67
(100+x)×1140=67
Multiplying both sides by 140:
100+x=6×1407
100+x=120
x=120−100=20
The contractor needs to employ 20 additional men to complete the work on time.
Topper's Solved these Questions
Similar Questions
A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?
View SolutionA contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men, how many days behind the schedule the work should have been finished? a. 5 b. 6 c. 7 d. 8
View Solution
Knowledge Check
- Question 1 - Select One
A contractor undertakes to do a piece of work in 40 days. He engages 100 men at eh beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional me, how many days behind the schedule the work should have been finished? 5 b. 6 c. 7 d. 8
A5B6C3D9 - Question 2 - Select One
A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men. Then after how many days from scheduled time the wrok would be finished?
A1. 4 daysB2. 5 daysC3. 8 daysD4. 7 days - Question 3 - Select One
A contractor undertakes to make a mall in 60 days and he
employs 30 men. After 30 days it is found that only one-
third of the work is completed. How many extre men should
he employ so that the work is completed on time?A20 menB25 menC30 menD40 men
A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
View SolutionA contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?
View SolutionA contract is to be completed in 92 days and 234 men set to work , each working 16h a day. After 66 days , 4/7 of the work is completed. How many additional men many be employed , so that the work may be completed in time , each man now working 18h a day ?
View SolutionA contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
View SolutionA contract is to be completed in 75 days and 187 men are to work 15 hours per day. After 65 days, 3/5 of the work is completed. How many additional men may be employed, so that the work may be completed in time each man now working 17 hours per day?
View Solution