Doubtnut Promotions Sticky

A contractor undertakes to do a piece of work in 96 days. He engages 100 men at the begin ning. But in the 1/6 of the scheduled time, 1/7 of work is completed. How many additional men should be employed so that the work will be com pleted in time?

A

30

B

20

C

15

D

10

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we can follow these calculations:

Step 1: Determine the total work and the time taken
The contractor has undertaken to complete the work in 96 days. We denote the total work as W.

Step 2: Calculate the time elapsed and work completed
In 16 of the scheduled time:
Time elapsed=966=16 days
In this time, 17 of the work is completed:
Work completed=W7

Step 3: Calculate the remaining work
The remaining work after 16 days is:
Remaining work=WW7=7W7W7=6W7

Step 4: Determine the remaining time
The total time for the project is 96 days, and 16 days have already been used. Thus, the remaining time is:
Remaining time=9616=80 days

Step 5: Set up the equation for the remaining work
Let x be the additional number of men needed. The total number of men working now is 100+x. The work rate for 100+x men over the remaining 80 days must equal the remaining work:
(100+x)×Rate×80=6W7

Step 6: Calculate the rate of work
The rate of work done by 100 men in 16 days is:
100×Rate×16=W7
From this, we can express the rate:
Rate=W7×100×16=W11200

Step 7: Substitute the rate into the remaining work equation
Substituting the rate back into the equation:
(100+x)×W11200×80=6W7

Step 8: Simplify the equation
Cancelling W from both sides:
(100+x)×8011200=67
(100+x)×1140=67
Multiplying both sides by 140:
100+x=6×1407
100+x=120

Step 9: Solve for x
x=120100=20

Final Answer
The contractor needs to employ 20 additional men to complete the work on time.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A contractor undertakes to do a piece of work in 40 days. He engages 100 men at eh beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional me, how many days behind the schedule the work should have been finished? 5 b.  6 c. 7 d. 8

    A5
    B6
    C3
    D9
  • Question 2 - Select One

    A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men. Then after how many days from scheduled time the wrok would be finished?

    A1. 4 days
    B2. 5 days
    C3. 8 days
    D4. 7 days
  • Question 3 - Select One

    A contractor undertakes to make a mall in 60 days and he
    employs 30 men. After 30 days it is found that only one-
    third of the work is completed. How many extre men should
    he employ so that the work is completed on time?

    A20 men
    B25 men
    C30 men
    D40 men