16 children can complete the work in 12 days, whereas 6 adults take 16 days to complete the same work. This work is started by 16 adults and after 3 days. 10 adults left the work, then, 4 children joined the work Accordingly, in how many days the remaining work get complete?
12 days
15 days
6 days
9 days
The correct Answer is:C
To solve the problem step by step, let's break it down:
Step 1: Determine the total work in terms of units
We know that 16 children can complete the work in 12 days.
- The total work done by 16 children in 12 days can be calculated as:
Total Work=Number of Children×Days=16×12=192 units
Step 2: Calculate the work done by 6 adults in 16 days
We also know that 6 adults can complete the same work in 16 days.
- The total work done by 6 adults in 16 days is also:
Total Work=6×16=96 units
Since both calculations represent the same total work, we can set them equal to each other to find the efficiency ratio between children and adults.
Step 3: Find the efficiency ratio of children and adults
From the previous calculations, we can find the efficiency of one adult in terms of children.
- Since 16 children do 192 units of work, the work done by 1 child in 1 day is:
Work per Child per Day=19216×12=1 unit
- For adults, since 6 adults do 192 units in 16 days, the work done by 1 adult in 1 day is:
Work per Adult per Day=1926×16=2 units
Thus, the ratio of efficiency of children to adults is:
Efficiency Ratio=1 (child):2 (adult)⇒2:1
Step 4: Work done by 16 adults in 3 days
Now, we need to calculate how much work is done by 16 adults in the first 3 days.
- Since 1 adult does 2 units of work per day, 16 adults will do:
Work done by 16 adults in 1 day=16×2=32 units
- Therefore, in 3 days, the work done is:
Total Work in 3 Days=32×3=96 units
Step 5: Calculate the remaining work
Now, we subtract the work done in the first 3 days from the total work to find the remaining work.
- Remaining work:
Remaining Work=192−96=96 units
Step 6: Work done after 3 days
After 3 days, 10 adults leave, leaving 6 adults. Then, 4 children join.
- Now we have 6 adults and 4 children working together. The work done by them in one day is:
Work done by 6 adults=6×2=12 units
Work done by 4 children=4×1=4 units
- Total work done by 6 adults and 4 children in one day:
Total Work in 1 Day=12+4=16 units
Step 7: Calculate the number of days to complete the remaining work
Now we need to find out how many days it will take to complete the remaining 96 units of work.
- Number of days required:
Days=Remaining WorkWork done in 1 Day=9616=6 days
Final Answer
Thus, the remaining work will be completed in 6 days.
---
We know that 16 children can complete the work in 12 days.
Total Work=Number of Children×Days=16×12=192 units
We also know that 6 adults can complete the same work in 16 days.
Total Work=6×16=96 units
Since both calculations represent the same total work, we can set them equal to each other to find the efficiency ratio between children and adults.
From the previous calculations, we can find the efficiency of one adult in terms of children.
Work per Child per Day=19216×12=1 unit
- For adults, since 6 adults do 192 units in 16 days, the work done by 1 adult in 1 day is:
Work per Adult per Day=1926×16=2 units
Efficiency Ratio=1 (child):2 (adult)⇒2:1
Now, we need to calculate how much work is done by 16 adults in the first 3 days.
Work done by 16 adults in 1 day=16×2=32 units
- Therefore, in 3 days, the work done is:
Total Work in 3 Days=32×3=96 units
Now, we subtract the work done in the first 3 days from the total work to find the remaining work.
Remaining Work=192−96=96 units
After 3 days, 10 adults leave, leaving 6 adults. Then, 4 children join.
Work done by 6 adults=6×2=12 units
Work done by 4 children=4×1=4 units
- Total work done by 6 adults and 4 children in one day:
Total Work in 1 Day=12+4=16 units
Now we need to find out how many days it will take to complete the remaining 96 units of work.
Days=Remaining WorkWork done in 1 Day=9616=6 days
Thus, the remaining work will be completed in 6 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
12 Men can complete one-third of the work in 8 days. In how many days can 16 men complete that work?
A18B12C24DCannot be determined - Question 2 - Select One
12 men can complete a piece of work in 16 days. In how many days will 4 men complete the same piece of work?
A60 daysB45 daysC54 daysD48 days - Question 3 - Select One
A' completes a work in 12 days 'B' completes the same work in 15 days .A started working alone and after 3 days B joined him .How many days will they now take together to complete the remaining work ?
A6B8C5D4
10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days.
View SolutionA can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?
View Solution‘A’ completes a work in 12 days. ‘B’ completes the same work in 15 days. ‘A’ started working alone and after 3 days B joined him. How many days will they now take together to complete the remaining work?
View Solution8 men can complete a work in 12 days, 4 women can complete it in 48 days and 10 children can complete the same work in 24 days. In how many days can 10 men, 4 women and 10 children complete the same work?
View Solution6 women alone can complete a piece of work in 10 days,
whereas 10 children alone take 15 days to complete the same
piece of work. How many days will 6 women and 10 children
together take to complete the piece of work ?View Solution