12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start working on the job and after working for two days, all of them stopped working. How many women should be put on the job to complete the remaining work, if It is to be completed in 3 days
15
22
18
Data inadequate
The correct Answer is:A
To solve the problem step by step, let's break it down:
Step 1: Calculate the total work done by men and women
We know that:
- 12 men can complete the work in 4 days.
- 15 women can also complete the same work in 4 days.
First, we calculate the total work in terms of man-days and woman-days.
Total work done by men:
Total Work=Number of Men×Days=12 men×4 days=48 man-days
Total work done by women:
Total Work=Number of Women×Days=15 women×4 days=60 woman-days
Step 2: Equate the total work done by men and women
Since both complete the same work:
48 man-days=60 woman-days
From this, we can find the efficiency ratio of men to women:
MW=6048=54
This means that 5 man-days are equivalent to 4 woman-days.
Step 3: Calculate the work done by 6 men in 2 days
Now, we need to find out how much work 6 men can do in 2 days.
The efficiency of 1 man is:
Efficiency of 1 man=48 man-days12 men×4 days=1 unit of work per day
Thus, the work done by 6 men in 1 day:
Work done by 6 men in 1 day=6 men×1 unit=6 units
In 2 days, the work done will be:
Total work done by 6 men in 2 days=6 units/day×2 days=12 units
Step 4: Calculate the remaining work
The total work is 48 units (from Step 1). The remaining work after 6 men have worked for 2 days is:
Remaining Work=48 units−12 units=36 units
Step 5: Determine how many women are needed to complete the remaining work in 3 days
Let x be the number of women needed to complete the remaining 36 units of work in 3 days.
The work done by x women in 3 days is:
Work done by x women in 3 days=x women×3 days×4 units1 woman=12x units
Setting this equal to the remaining work:
12x=36
Step 6: Solve for x
Dividing both sides by 12:
x=3612=3
Conclusion
Thus, 3 women are needed to complete the remaining work in 3 days.
---
We know that:
- 12 men can complete the work in 4 days.
- 15 women can also complete the same work in 4 days.
Total Work=Number of Men×Days=12 men×4 days=48 man-days
Total Work=Number of Women×Days=15 women×4 days=60 woman-days
Since both complete the same work:
48 man-days=60 woman-days
MW=6048=54
This means that 5 man-days are equivalent to 4 woman-days.
Now, we need to find out how much work 6 men can do in 2 days.
Efficiency of 1 man=48 man-days12 men×4 days=1 unit of work per day
Work done by 6 men in 1 day=6 men×1 unit=6 units
Total work done by 6 men in 2 days=6 units/day×2 days=12 units
The total work is 48 units (from Step 1). The remaining work after 6 men have worked for 2 days is:
Remaining Work=48 units−12 units=36 units
Let x be the number of women needed to complete the remaining 36 units of work in 3 days.
Work done by x women in 3 days=x women×3 days×4 units1 woman=12x units
12x=36
Dividing both sides by 12:
x=3612=3
Thus, 3 women are needed to complete the remaining work in 3 days.
Topper's Solved these Questions
Similar Questions
12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start’ working on the job and after working for 2 days, all of them stopped working. How many women should be put on the job to Complete the remaining work, if it is to be completed in 3 days?
View SolutionTwenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days.Sixteen men and sixteen women started working and worked for twelve days. How many more men are to be added to complete the remaining work in 2 days?
View Solution
Knowledge Check
- Question 1 - Select One
15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
A40B42C38D32 - Question 2 - Select One
12 men can complete a work in 16 days and 16 women can complete the same work in 12 days In how many days will 4 men and 8 women complete that work ?
A16B12C18D10 - Question 3 - Select One
10 men can complete a piece of work in 15 days and 15 women can complete the same work in 12 days. If all the 10 men and 15 women work together, in how many days will the work get completed?
A6B613C623D723
12 men can complete a piece of work in 16 days. In how many days will 4 men complete the same piece of work?
View Solution21 men can complete a piece of work in 427 days. In how many days can 18 men complete the same piece of work?
View SolutionTwenty four men can complete a work in sixteen days. Thirty two women can complete the same work in twenty four days. Sixteen men and sixteen women started working and worked for 12 days. How many more. men are to be added to complete the remaining work in 2 days ?
View SolutionTwenty four men can complete a work in sixteen days. Thirty two women can complete the same work in twenty four days. Sixteen men and sixteen women started working and worked for 12 days. How many more. men are to be added to complete the remaining work in 2 days ?
View Solution24 boys can complete a work in 12 days while 16 men can complete the same work in 9 days. In how many days will 12 boys and 12 men together complete the same work ?
View Solution