12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start working on the job and after working for two days, all of them stopped working. How many women should be put on the job to complete the remaining work, if It is to be completed in 3 days

A

15

B

22

C

18

D

Data inadequate

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, let's break it down:

Step 1: Calculate the total work done by men and women
We know that:
- 12 men can complete the work in 4 days.
- 15 women can also complete the same work in 4 days.

First, we calculate the total work in terms of man-days and woman-days.

Total work done by men:
Total Work=Number of Men×Days=12 men×4 days=48 man-days

Total work done by women:
Total Work=Number of Women×Days=15 women×4 days=60 woman-days

Step 2: Equate the total work done by men and women
Since both complete the same work:
48 man-days=60 woman-days

From this, we can find the efficiency ratio of men to women:
MW=6048=54
This means that 5 man-days are equivalent to 4 woman-days.

Step 3: Calculate the work done by 6 men in 2 days
Now, we need to find out how much work 6 men can do in 2 days.

The efficiency of 1 man is:
Efficiency of 1 man=48 man-days12 men×4 days=1 unit of work per day

Thus, the work done by 6 men in 1 day:
Work done by 6 men in 1 day=6 men×1 unit=6 units

In 2 days, the work done will be:
Total work done by 6 men in 2 days=6 units/day×2 days=12 units

Step 4: Calculate the remaining work
The total work is 48 units (from Step 1). The remaining work after 6 men have worked for 2 days is:
Remaining Work=48 units12 units=36 units

Step 5: Determine how many women are needed to complete the remaining work in 3 days
Let x be the number of women needed to complete the remaining 36 units of work in 3 days.

The work done by x women in 3 days is:
Work done by x women in 3 days=x women×3 days×4 units1 woman=12x units

Setting this equal to the remaining work:
12x=36

Step 6: Solve for x
Dividing both sides by 12:
x=3612=3

Conclusion
Thus, 3 women are needed to complete the remaining work in 3 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • 15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?

    A40
    B42
    C38
    D32
  • 12 men can complete a work in 16 days and 16 women can complete the same work in 12 days In how many days will 4 men and 8 women complete that work ?

    A16
    B12
    C18
    D10
  • 10 men can complete a piece of work in 15 days and 15 women can complete the same work in 12 days. If all the 10 men and 15 women work together, in how many days will the work get completed?

    A6
    B613
    C623
    D723