Doubtnut Promotions Sticky

A contract is to be completed in 50 days and 105 men were
set to work, each working 8 h a day. After 25 days, 2/5 th of
the work is finished. How many additional men be employed,
so that the work may be completed on time, each man now
working 9 h a day?

A

34

B

36

C

35

D

37

Text Solution
Verified by Experts

The correct Answer is:(c)


According to the formula,
M1D1T1W1=M2D2T2w2 (by technique 1 )
Given M1=105,D1=25,T1=8,W1=25
Now, let the additional men be x.
Then, M2=105+x,T2=9
D2=25
And W2=125+35
On putting these values in the above formula
105×25×82/5=(105+x)×25×93/5
=105×82=(105+x)×93
=105×4=(105+x)×3
=105×4=105×3+3x
3x=105
x=35 men

Doubtnut Promotions Banner
|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?

    A35
    B40
    C45
    DNone of these
  • Question 2 - Select One

    A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?

    A60
    B56
    C70
    D42
  • Question 3 - Select One

    A contract is to be completed in 92 days and 234 men set to work , each working 16h a day. After 66 days , 4/7 of the work is completed. How many additional men many be employed , so that the work may be completed in time , each man now working 18h a day ?

    A162
    B234
    C262
    D81