Doubtnut Promotions Sticky

A,B,C,D and E are five persons to complete jobs X and Y. Line graph shows the data regarding the number of days taken by these persons to complete the job X and Y.
A,B,C,D and E are five persons to complete jobs X and Y. Line graph shows the data regarding the number of days taken by these persons to complete the job X and Y.      If A worked on job X for 5 days each and C worked for 3 days. the remaining job was done by E and D. If the ratio of the number of days for which D and E worked is in ratio 1:1, then find the number of days for which C, D and E worked?
If A worked on job X for 5 days each and C worked for 3 days. the remaining job was done by E and D. If the ratio of the number of days for which D and E worked is in ratio 1:1, then find the number of days for which C, D and E worked?

A

6

B

3

C

9

D

5

Video Solution
Doubtnut Promotions Banner
|
Answer

Step by step video & image solution for A,B,C,D and E are five persons to complete jobs X and Y. Line graph shows the data regarding the number of days taken by these persons to complete the job X and Y. If A worked on job X for 5 days each and C worked for 3 days. the remaining job was done by E and D. If the ratio of the number of days for which D and E worked is in ratio 1:1, then find the number of days for which C, D and E worked? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 40 men can complete a job in 6 days, then find the number fo days taken by 60 men to complete it.

    A3
    B10
    C12
    D4
  • Question 2 - Select One

    A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2. In how many days can the faster person complete the job?

    A50
    B30
    C40
    D60
  • Question 3 - Select One

    X can complete a job in 12 days. If X and Y work together, they can complete the job in 6 days. Y alone can complete the job in

    A10 days
    B12 days
    C15 days
    D18 days