Doubtnut Promotions Sticky

The information about numbers of workers and number of days to complete a work is given in the following table. Complete the table.
Number of workers302010Days691236

Text Solution
Verified by Experts

The correct Answer is:Number of workers 15 and 5 respectively, days = 18

|
Updated on:21/07/2023

Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 40 workers can complete a task in 24 days, then, find the time taken by 16 workers to complete twice the work.

    A125 days
    B122 days
    C120 days
    D116 days
  • Question 2 - Select One

    42 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:

    A7
    B6
    C14
    D16
  • Question 3 - Select One

    56 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:

    A7
    B8
    C14
    D16