The information about numbers of workers and number of days to complete a work is given in the following table. Complete the table.
Number of workers302010Days691236
The correct Answer is:Number of workers 15 and 5 respectively, days = 18
Similar Questions
The following table shows classification of number of workers and the number of hours they work in a software company.Find the median of the number of hours they work.
View SolutionThe following table shows classification of number of workers and the number of hours they work in a software company. Find the median of the number of hours they work.
View Solution
Knowledge Check
- Question 1 - Select One
If 40 workers can complete a task in 24 days, then, find the time taken by 16 workers to complete twice the work.
A125 daysB122 daysC120 daysD116 days - Question 2 - Select One
42 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:
A7B6C14D16 - Question 3 - Select One
56 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:
A7B8C14D16
The following table shows classification of number of workers and the number of hours they work in a software company. Find the median of the number of hours they work.
View SolutionIf 12 men can finish a work in 20 days , then find the number of days required to complete the same work by15 men .
View SolutionThe following table gives the number of pages written by Saria for completing her own book for 30 days.
Find the mean number of pages written per day.View Solution24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
View SolutionA work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:
View Solution