A,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?

A

5

B

4

C

3

D

6

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:A

Updated on:21/07/2023
|
Answer

Step by step video, text & image solution for A,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work? by Maths experts to help you in doubts & scoring excellent marks in Class 8 exams.

Updated on:21/07/2023


Similar Questions


Knowledge Check

  • A and B can do a piece of work in 24 and 30 days respectively.
    Both started the work and worked for 6 days. Then B leaves
    the work and C joins and the remaining work is completed by A and C together in 11 days. Find the days in which C
    alone can do the work

    A80
    B100
    C120
    D130
  • A, b and C can alone complete a work in 10, 12 and 15 days
    respectively. A and C started the work and after working for
    4 days, A left and B joined. In how many days the total work
    was completed ?

    A659days
    B629days
    C6 days
    D549days
  • A, B and C, one can do a piece of work in 9, 12 and 18 days respectively. They all started the work together, but A left after 3 days. In how many days, was the remaining work completed?

    A2
    B52
    C114
    D95