A work could be completed in 100 days by some workers. However due to the absence of 10 workers it was completed in 110 days. The original number of workers was : a 100 b 110 c 55 d 50
Correct option b 110 Explanation:let total No. of worker in beginning in ‘N’ According to question
Related Solutions
A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:
View SolutionA work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:
View SolutionA work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:
View Solutionकुछ मजदूर किसी काम को 100 दिनों में ख़त्म कर सकते थे , लेकिन 10 मजदुर की अनुपस्तिति के कारण काम 110 दिनों में ख़त्म हुआ , तो मजदूरों की आरभिक संख्या क्या थी ?
View SolutionThe information about numbers of workers and number of days to complete a work is given in the following table. Complete the table.
View SolutionHow many workers are required for completing the construction work in the 10 days ?
(i) of the work can be completed by 8 workers in 8 days.
(ii) 20 workers can complete the work in 16 days.
(iii) One - eighth of the work can ve completed by 8 workers in 5 days.
View Solution45 मजदूर एक काम को 27 दिनों में पूरा करते हैं तो कितने मजदूर उसी काम को 15 दिनों में पूरा करेंगे?
View SolutionA group of workers promise to complete a piece of work in 10 days, but five of them do not report for work. If it took the remaining workers 12 days to complete the work, then the number of workers originally hired was b. c. d.
View Solution56 workers canfinish a piece of work in 14 days. If the work
is to be completed in 8 days, then how many extra workers
are required ?
View Solution100 workers finish a work in 20, days. How many workers are required to finish the work in 25 days ?
View Solution20 workers working for 5 hours a day complete a work in 10 days . If 25 workers are employed to work 10 hours a day, what is the time required to complete the work ?
View Solution20 workers working for 5 h per day complete a work in 10 days. If 25 workers are employed to work 10 h per day, what is the time required to complete the work?
View Solutionएक कार्य कुछ व्यक्तियों द्वारा 100 दिनों में पूरा किया जा सकता था। किन्तु 10 व्यक्तियों की अनुपस्थिति के कारण वह 110 दिनों में पूरा हो पाया। प्रारम्भ में कितने व्यक्ति काम पर लगाए गए।
View Solutionਕਿਸੇ ਕੰਮ ਨੂੰ ਕੁਝ ਦਿਨਾਂ ਵਿੱਚ ਪੂਰਾ ਕਰਨ ਲਈ 150 ਮਜ਼ਦੂਰ ਲਗਾਏ ਗਏ। ਦੂਜੇ ਦਿਨ 4 ਮਜ਼ਦੂਰਾਂ ਨੇ ਕੰਮ ਛੱਡ ਦਿੱਤਾ, ਤੀਜੇ ਦਿਨ 4 ਹੋਰ ਕਰਮਚਾਰੀਆਂ ਨੇ ਕੰਮ ਛੱਡ ਦਿੱਤਾ ਅਤੇ ਇਸ ਤਰ੍ਹਾਂ ਹੋਰਾਂ ਨੇ।ਹੁਣ ਕੰਮ ਪੂਰਾ ਕਰਨ ਵਿੱਚ 8 ਦਿਨ ਵੱਧ ਲੱਗਦੇ ਹਨ ਤਾਂ ਦਿਨਾਂ ਦੀ ਸੰਖਿਆ ਦੱਸੋ ਜਿਸ ਵਿੱਚ ਕੰਮ ਪੂਰਾ ਕੀਤਾ ਗਿਆ।
View Solutionकामगार दिन में घण्टे काम कर एक काम को दिनों में पूरा करते है। यदि कामगारों को दिन में घण्टे काम करने के लिए लगाया जाता है तो काम के पूरा होने का आवश्यक समय क्या है ?
View SolutionA company employed 200 workers to complete a certain work in 150 days. If only one-fourth of the work has been done in 50 days, then in order to complete the whole work in time, the number of additional workers to be employed was
View Solutionएक कंपनी ने 150 दिन में किसी काम को पूरा करने के लिए 200 कामगारों को नियक्त किया यदि 50 दिन में केवल एक चौथाई काम पूरा हुआ हो तो पुरे काम को समय पर पूरा करने में कितने अतिरिक्त कामगार लगाने पड़ेगे ?
View Solution56 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:
View Solution42 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:
View SolutionIf 40 workers can complete a task in 24 days, then, find the time taken by 16 workers to complete twice the work.
View Solution