Doubtnut Promotions Sticky

P works 25% more efficinetly than Q and Q works 50% more efficiently than R. To complete a certain project. P alone takes 50 days less than Q. if in this project. P alone works for 60 dasy and then Q alone works for 125 days, then in how many days car R alone can complete the remaining work?

A

50

B

75

C

100

D

150

Video Solution
Text Solution
Verified by Experts

The correct Answer is:B


(i) Let th amount of work done by R in a day be x units
(ii) Let the efficine or R be 100
Efficiency of Q =150 and Efficinency of P=187.5
(iii) Now find the ratio of the effciencies of P,Q and R
(iv) Then the find the rato of time taken by P,Q to complete the work

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    P and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?

    A48 days
    B42 days
    C45 days
    D51 days
  • Question 2 - Select One

    A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?

    A4
    B15
    C154
    D16
  • Question 3 - Select One

    A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?

    A60 days
    B36 days
    C45 days
    D24 days