A is twice as good a workman as B. A takes 6 days to comlete a task. What time does B take to complete the work (in days)?
3
6
9
12
The correct Answer is:D
To solve the problem, we need to determine how long it takes for workman B to complete the task, given that A is twice as efficient as B and A takes 6 days to complete the task.
1. Understand the Efficiency Relationship:
- Since A is twice as good a workman as B, we can say that if B's efficiency is 1 unit of work per day, then A's efficiency is 2 units of work per day.
2. Calculate Total Work Done by A:
- A completes the task in 6 days. Therefore, the total work can be calculated as:
Total Work=Efficiency of A×Time taken by A
Substituting the values:
Total Work=2 units/day×6 days=12 units
3. Determine the Time Taken by B:
- Now that we know the total work is 12 units and B's efficiency is 1 unit of work per day, we can find out how many days B will take to complete the same work:
Time taken by B=Total WorkEfficiency of B=12 units1 unit/day=12 days
Final Answer:
B takes 12 days to complete the work.
---
- Since A is twice as good a workman as B, we can say that if B's efficiency is 1 unit of work per day, then A's efficiency is 2 units of work per day.
- A completes the task in 6 days. Therefore, the total work can be calculated as:
Total Work=Efficiency of A×Time taken by A
Substituting the values:
Total Work=2 units/day×6 days=12 units
- Now that we know the total work is 12 units and B's efficiency is 1 unit of work per day, we can find out how many days B will take to complete the same work:
Time taken by B=Total WorkEfficiency of B=12 units1 unit/day=12 days
B takes 12 days to complete the work.
Topper's Solved these Questions
- TIME AND WORKBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 3
21 Videos
- TIME AND WORKBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 1
30 Videos
- BANKING AND COMPUTINGBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - BANKING AND COMPUTINGEXERCISE - Level 3
6 Videos
Similar Questions
A is twice as good workman as B.A takes 6 days the complete a work. In what time can B complete the work?
View SolutionC is 5 times as productive as B. A takes 60 days to complete a task. If A, B and C work together they can complete the task in 12 days. In how many days can B complete the task if he worked alone ?
View Solution
Knowledge Check
A is thrice as good a workman as B and takes 10 days less to do a piece of work than B takes. The number of days taken by B to finish the work is :
A12 daysB15 daysC20 daysD30 daysA is thrice as good a workman as B. If B takes 45 days to finish a task, then how many days will A take to finish the same task?
A20B30C5D15L is twice as good a work man as U. If U takes 45 days to finish a task, then how many days will L take to finish the task ?
A22(32) daysB22 daysC22(12) daysD21 days
C is 5 times as productive as B. A takes 60 days to complete a task. If A, B and C work together they can complete the task in 12 days. In how many days can B complete the task if he worked alone ?
View SolutionA is thrice as good a workman as B. C alone takes 48 days to paint a house. All three A, B and C working together take 16 days a point the house. It will take how many days for B alone to paint the house ?
View SolutionA is thrice as good a workman as B. C alone takes 48 days to paint a house. All three A, B and C working together take 16 days a point the house. It will take how many days for B alone to paint the house ?
View SolutionA is thrice as good a workman as B and takes 10 days less to do a piece of work than B takes. The number of days taken by B to finish the work is :
View SolutionA is twice as good a workman as B and therefore A takes 6 days less than B to finish the work individually. If A and B working complete together the work in 4 days, then how many days are required by B to complete the work alone?
View Solution