A is twice as good a workman as B. A takes 6 days to comlete a task. What time does B take to complete the work (in days)?

A

3

B

6

C

9

D

12

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem, we need to determine how long it takes for workman B to complete the task, given that A is twice as efficient as B and A takes 6 days to complete the task.

1. Understand the Efficiency Relationship:
- Since A is twice as good a workman as B, we can say that if B's efficiency is 1 unit of work per day, then A's efficiency is 2 units of work per day.

2. Calculate Total Work Done by A:
- A completes the task in 6 days. Therefore, the total work can be calculated as:
Total Work=Efficiency of A×Time taken by A
Substituting the values:
Total Work=2 units/day×6 days=12 units

3. Determine the Time Taken by B:
- Now that we know the total work is 12 units and B's efficiency is 1 unit of work per day, we can find out how many days B will take to complete the same work:
Time taken by B=Total WorkEfficiency of B=12 units1 unit/day=12 days

Final Answer:
B takes 12 days to complete the work.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A is thrice as good a workman as B and takes 10 days less to do a piece of work than B takes. The number of days taken by B to finish the work is :

    A12 days
    B15 days
    C20 days
    D30 days
  • A is thrice as good a workman as B. If B takes 45 days to finish a task, then how many days will A take to finish the same task?

    A20
    B30
    C5
    D15
  • L is twice as good a work man as U. If U takes 45 days to finish a task, then how many days will L take to finish the task ?

    A22(32) days
    B22 days
    C22(12) days
    D21 days