Doubtnut Promotions Sticky

27 men can dig a well in 20 days working 5 hours a day. They start digging it. After 4 days, 12 men leave. How hourse a day should the remaining men work to complete digging it by the scheduled date ?

A

6

B

8

C

10

D

9

Video Solution
Text Solution
Verified by Experts

The correct Answer is:D


Let the requred number of hours pe day b h.
Let the work done by each man be 1 unit/hr /
The time for which 27 men worked in the first our days =(5)(4) hours =20 hours
Work complete in the first 4 days =(27)(1)(20) units =540 units
Renaining in time =(204)(h) hours =16 h hours.
Completed in the remaining time =(2712)(1)(16h) units =240 h units
Total time taken =(5)(20) hours=100 hours
Total work =(27)(1)(100) units =2700 units 2700+540+240h
9 hours

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 4 men can reap a field in 5 days working 12 hours a day, in how many days can 10 men reap the same field working 8 hours a day?

    A3
    B2
    C4
    D6
  • Question 2 - Select One

    8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?

    A2
    B3
    C4
    D5
  • Question 3 - Select One

    8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finIsh the work. In how many days would the remaining work be completed?

    A2
    B3
    C4
    D5