P car complete a piece of wark in 3 days. Q takes triple the time taken by P,R takes 4 times that taken by Q and s takes double the time taken by R to complete the same task. They are grouped in two pairs. One of the pairs takes 212 times the taken by the other pair to complete the work. which is the second pair?

A

P,S

B

R,R

C

Q,R

D

Q,S

Text Solution
Verified by Experts

The correct Answer is:A


(i)Q and R take 9 days 36 days respecrtively to complete a piece of work
(ii) Let P take x days, Q takes 3x days, R take 12x days and S take 24 x days
(iii) Find the part of the work done by each perosn, per day.
(iv) Then check from the option

Updated on:21/07/2023
Doubtnut Promotions Banner
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can complete a piece of work in 4 days. B takes double the time taken by A, C takes double that of B, and D takes double that of C to complete the same task. They are paired in groups of two each. One pair takes two-thirds the time needed by the second pair to complete the work. Which is the first pair?

    AA and B
    BA and C
    CB and C
    DA and D
  • A can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.

    A8 days
    B10 days
    C6 days
    D9 days
  • A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is

    A10 days
    B12 days
    C15 days
    D16 days