P car complete a piece of wark in 3 days. Q takes triple the time taken by P,R takes 4 times that taken by Q and s takes double the time taken by R to complete the same task. They are grouped in two pairs. One of the pairs takes 212 times the taken by the other pair to complete the work. which is the second pair?
P,S
R,R
Q,R
Q,S
The correct Answer is:A
(i)Q and R take 9 days 36 days respecrtively to complete a piece of work
(ii) Let P take x days, Q takes 3x days, R take 12x days and S take 24 x days
(iii) Find the part of the work done by each perosn, per day.
(iv) Then check from the option
Topper's Solved these Questions
- TIME AND WORKBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 3
21 Videos
- TIME AND WORKBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 1
30 Videos
- BANKING AND COMPUTINGBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - BANKING AND COMPUTINGEXERCISE - Level 3
6 Videos
Similar Questions
A can do a work in 5 days less than the time taken by B to do it. If both of them together take 1119days, then the time taken by B alone to the same work (in days) is
View SolutionA can complete a work in 12 days and B complete the same work in 15 days. Find the time taken by them when A and B worked together.
View Solution
Knowledge Check
A can complete a piece of work in 4 days. B takes double the time taken by A, C takes double that of B, and D takes double that of C to complete the same task. They are paired in groups of two each. One pair takes two-thirds the time needed by the second pair to complete the work. Which is the first pair?
AA and BBA and CCB and CDA and DA can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.
A8 daysB10 daysC6 daysD9 daysA can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is
A10 daysB12 daysC15 daysD16 days
Time taken by A to complete a work is 7 days more than the time taken by B to complete the same work. Working together they can complete the work in 12 days. In what time can A alone complete the work ?
View Solution6 children and 2 men complete a certain piece of work in 6 days. Each child takes twice the time taken by a man to finish the work In how many days will 5 men finish the same work?
View Solution6 children and 2 men complete a certain piece of work in 6 days. Each child takes twice the time taken by a man to finish the work. In how many days will 5 men finish the same work?
View SolutionIf 40 workers can complete a task in 24 days, then, find the time taken by 16 workers to complete twice the work.
View SolutionA can complete a piece of work in 18 days and B can complete the same work in half time taken by A. Then, working together, what part of the same work they can complete in a day?
View Solution