P,Q and R together can complete 50% of a work in 2 days. All three start the work but after two days Q. left. P and R alone in 8 days. In how many days can P alone complete the work?
6
8
10
12
The correct Answer is:B
(i) Remaining work ' two day's work s one day work.
(iii) Let p,q nad r be the numbr of days taken by P,Q and R respectively.
(iv) Sovle the above equations fo find the P
Topper's Solved these Questions
- TIME AND WORKBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 3
21 Videos
- TIME AND WORKBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 1
30 Videos
- BANKING AND COMPUTINGBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - BANKING AND COMPUTINGEXERCISE - Level 3
6 Videos
Similar Questions
Knowledge Check
A and B together can complete a work in 10 days. They started together but A left after 2 days and the remaining work was completed by B in 12 days. In how many days can A complete the entire work while working alone?
A15B20C30D45A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
A60 daysB36 daysC45 daysD24 daysIf A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many day can A alone complete the work?
A60 daysB45 daysC40 daysD30 days
A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View SolutionA and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
View SolutionA and B together can complete a work in 30 days. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?
View SolutionA and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in
View SolutionA and B together can complete a work in 20 days. They started together but after 4 days A left the work. The remaining work was completed by B alone in 24 more days. In how many days can A complete the entire work alone?
View Solution