Doubtnut Promotions Sticky

P,Q and R together can complete 50% of a work in 2 days. All three start the work but after two days Q. left. P and R alone in 8 days. In how many days can P alone complete the work?

A

6

B

8

C

10

D

12

Text Solution
Verified by Experts

The correct Answer is:B


(i) Remaining work = 1 - ( P + Q + R ) ' two day's work - ( P + R ) s one day work.
(iii) Let p,q nad r be the numbr of days taken by P,Q and R respectively.
( i i i ) 1 q + 1 p + 1 r = 1 4 ( 1 )
1 p + 1 r = 1 6 ( 2 )
3 q + 2 q + 11 r = 1 ( 3 )
(iv) Sovle the above equations fo find the P

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B together can complete a work in 10 days. They started together but A left after 2 days and the remaining work was completed by B in 12 days. In how many days can A complete the entire work while working alone?

    A15
    B20
    C30
    D45
  • Question 2 - Select One

    A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?

    A60 days
    B36 days
    C45 days
    D24 days
  • Question 3 - Select One

    If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many day can A alone complete the work?

    A60 days
    B45 days
    C40 days
    D30 days