Doubtnut Promotions Sticky

Fatima and Zahira can do a piece of work in 12 days and 15 days respectively. If they work for alternate day and Fatima starts the work first, then in how many days the work will be completed?

A

1215

B

1314

C

1315

D

15

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we need to determine how many days Fatima and Zahira will take to complete the work when they work alternately, starting with Fatima.

Step 1: Determine the total work
We will calculate the total work based on the least common multiple (LCM) of the days taken by Fatima and Zahira to complete the work.

- Fatima can complete the work in 12 days.
- Zahira can complete the work in 15 days.

LCM of 12 and 15:
- The prime factorization of 12 is 22×3.
- The prime factorization of 15 is 3×5.
- The LCM is 22×3×5=60.

So, the total work is 60 units.

Step 2: Calculate the work done by each person in one day
Now, we will find out how much work each person can do in one day.

- Work done by Fatima in one day:
Fatima's work per day=60 units12 days=5 units/day

- Work done by Zahira in one day:
Zahira's work per day=60 units15 days=4 units/day

Step 3: Calculate the total work done in two days
Since they work on alternate days, we will calculate the total work done in a 2-day cycle (1 day by Fatima and 1 day by Zahira).

- Work done in 2 days:
Total work in 2 days=Fatima's work+Zahira's work=5+4=9 units

Step 4: Determine how many complete 2-day cycles are needed
Now, we need to find out how many complete 2-day cycles are required to get close to 60 units of work.

- Total work done in n cycles of 2 days:
Total work in n cycles=9n units

To find n:
9n60n6096.67
So, the maximum complete cycles n=6.

Step 5: Calculate the total work done after 12 days
After 6 complete cycles (12 days):
Total work done=9×6=54 units

Step 6: Calculate the remaining work
Now, we need to find out how much work is left after 12 days:
Remaining work=6054=6 units

Step 7: Determine who works on the 13th day
On the 13th day, it will be Fatima's turn to work again. She can do 5 units of work in one day.

- After Fatima works on the 13th day:
Work done on 13th day=5 units
Remaining work after 13th day=65=1 unit

Step 8: Determine how much time Zahira will take to finish the remaining work
On the 14th day, it will be Zahira's turn to work. She can do 4 units of work in one day.

To finish the remaining 1 unit of work, Zahira will take:
Time taken by Zahira=1 unit4 units/day=14 days

Step 9: Calculate the total time taken
Total time taken to complete the work:
Total days=13+14=1314 days

Final Answer
The work will be completed in 1314 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Fatima and Zahira can do a piece of work in 12 days and 15 days respectively. If they work for alternate day and Fatima starts the work first, then in how many days the work will be completed?

    A1215
    B1314
    C1315
    D15
  • Question 2 - Select One

    Arun and Amit can do a piece of work in 9 days and 12 days respectively . If they work for alternate days and Amit starts the work first , then in how many days 35/36 parts of whole work will be completed ?

    A10 days
    B12 days
    C5 days
    D8 days
  • Question 3 - Select One

    A and B can complete a piece of work in 4 days and 8 days, respctively. They work on alternate days and A starts the work. In how work in may days will the work be completed

    A3
    B4
    C5
    D6