Doubtnut Promotions Sticky

In the previous question (number 33) if Zahira starts first then in how many days, the work will be completed?

A

1415

B

14

C

1315

D

1325

Text Solution
Verified by Experts

The correct Answer is:D

Doubtnut Promotions Banner
|
Updated on:21/07/2023

Related Playlists


Knowledge Check

  • Question 1 - Select One

    The first term of an A.P. is 3 and its common difference is 4. The 11th term is

    A(a) 39
    B(b) 41
    C(c) 43
    D(d) 45
  • Question 1 - Select One

    Fatima and Zahira can do a piece of work in 12 days and 15 days respectively. If they work for alternate day and Fatima starts the work first, then in how many days the work will be completed?

    A1215
    B1314
    C1315
    D15
  • Question 1 - Select One

    Arun and Amit can do a piece of work in 9 days and 12 days respectively . If they work for alternate days and Amit starts the work first , then in how many days 35/36 parts of whole work will be completed ?

    A10 days
    B12 days
    C5 days
    D8 days
  • Question 1 - Select One

    A is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?

    A17
    B19
    C19.5
    D21
  • Question 1 - Select One

    A is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?

    A17
    B19
    C19.5
    D21
  • Question 1 - Select One

    Fatima and Zahira can do a piece of work in 12 days and 15 days respectively. If they work for alternate day and Fatima starts the work first, then in how many days the work will be completed?

    A1215
    B1314
    C1315
    D15
  • Question 1 - Select One

    A can do a work in 6 days, B can do it in 8 days and C can complete it in 12 days. If A starts the work and they work in alternatively, then in how many days, the work will be completed?

    A635
    B723
    C525
    D623
  • Question 1 - Select One

    The number of days required by A, B and C to work individually is 6, 12 and 8 respectively. They started a work doing it alternatively. If A has started then followed by B and so on, how many days are needed to complete the whole work?
    In the above question if the order of working days be as B,C,A,B,C,A…(starting with B and followed by C and A respectively), then in how many days the work will he completed?

    A734
    B8
    C814
    D9

Similar Questions